5036 N RIVERTON AVE 91601
Certificate Information: 5036 N RIVERTON AVE 91601
- Application / Permit
- 19030-20000-00167
- Plan Check / Job No.
- B19VN00450
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR (3) 3-STORY DUPLEX W/ ATTACHED GARAGES -- NON HILLSIDE GRADING AREA
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/3/2024
Permit Application Status History
| Submitted | 1/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/29/2019 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 1/29/2019 | APPLICANT |
| Quality Review Completed | 1/31/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 2/5/2019 | APPLICANT |
| Applicant returned to address corrections | 4/18/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 8/13/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/15/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/17/2020 | NILOOFAR MEHRAIN |
| Issued | 2/9/2021 | APPLICANT |
| Permit Finaled | 1/3/2024 | MANUEL TEJADA |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 6/10/2020 | GISELLE CORELLA |
| ZI | Cleared | 6/10/2020 | GISELLE CORELLA |
| CPC | Cleared | 9/16/2020 | PABLO ESTRADA |
Contact Information
| Contractor | Ozair Construction & Design Inc; Lic. No.: 992682-B | 2228 LAUREL CANYON BLVD LOS ANGELES, CA 90045 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 2/11/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Bottom/Toe | 2/18/2021 | Partial Inspection | TIMOTHY POWELL |
| Bottom/Toe | 2/19/2021 | Partial Approval | TIMOTHY POWELL |
| Excavation | 2/19/2021 | Partial Approval | TIMOTHY POWELL |
| Deputy Grading | 2/24/2021 | Approved | TIMOTHY POWELL |
| Excavation | 2/25/2021 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 2/26/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/1/2021 | Conditional Approval | TIMOTHY POWELL |
| Bottom/Toe | 12/19/2023 | Approved | MANUEL TEJADA |
| Final | 12/19/2023 | Corrections Issued | MANUEL TEJADA |
| Rough | 12/19/2023 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 12/20/2023 | Approved | MANUEL TEJADA |
| Final | 1/3/2024 | Permit Finaled | MANUEL TEJADA |