10810 W VANOWEN ST 91605
Certificate Information: 10810 W VANOWEN ST 91605
- Application / Permit
- 19030-10000-08437
- Plan Check / Job No.
- B19LA27117
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE WORK/GRADING FOR THE CONSTRUCTION OF A NEW 3-STORY WAREHOUSE FACILITY, (2,130CY)
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/2/2023
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 1/23/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/7/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 3/11/2020 | APPLICANT |
| Applicant returned to address corrections | 9/15/2020 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 11/2/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 2/8/2022 | SERGIO GUTIERREZ |
| Issued | 2/14/2022 | APPLICANT |
| Permit Finaled | 2/1/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 9/17/2021 | AMMAR ELTAWIL |
| Grading Pre-Inspection | Cleared | 2/8/2022 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Vcc Llc; Lic. No.: 970830-B | P O BOX 555 LITTLE ROCK, AR 72203 |
| Engineer | Mckee,, Christopher Shannon; Lic. No.: C74414 | 160 S OLD SPRINGS RD STE 210 ANAHEIM, CA 92808 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 2/15/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 2/22/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Bottom/Toe | 3/1/2022 | Approved | ALEXANDER HELFER |
| Deputy Grading | 3/1/2022 | Approved | ALEXANDER HELFER |
| Deputy Grading | 3/2/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/3/2022 | No Access for Inspection | MATTHEW JENKINS |
| Deputy Grading | 3/4/2022 | Approved | MANUEL TEJADA |
| Deputy Grading | 3/7/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/8/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/9/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/10/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/11/2022 | Approved | TIMOTHY POWELL |
| Approved Compaction Report | 3/14/2022 | Partial Approval | TIMOTHY POWELL |
| Private Sewage Disposal System | 3/18/2022 | Partial Inspection | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 3/21/2022 | Partial Approval | BRIAN MILLER |
| Approved Compaction Report | 3/22/2022 | Approved | TIMOTHY POWELL |
| Drainage Devices/Catch Basin | 3/25/2022 | Partial Approval | BRIAN MILLER |
| Excavation | 4/12/2022 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 4/27/2022 | Partial Approval | MANUEL TEJADA |
| Excavation | 5/13/2022 | Approved | VASIL MIHALEV |
| Rough | 5/25/2022 | Approved | VASIL MIHALEV |
| Sub-Drain | 6/15/2022 | Not Ready for Inspection | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 7/5/2022 | Partial Approval | TIMOTHY POWELL |
| Drainage Devices/Catch Basin | 7/15/2022 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 11/16/2022 | Approved | VASIL MIHALEV |
| Drainage Devices/Catch Basin | 11/17/2022 | Approved | VASIL MIHALEV |
| Final | 2/1/2023 | Permit Finaled | MANUEL TEJADA |