200 E WASHINGTON BLVD 90015
Certificate Information: 200 E WASHINGTON BLVD 90015
- Application / Permit
- 19030-10000-08335
- Plan Check / Job No.
- B19LA26875
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE PREPARATION & EXCAVATION & BACKFILL FOR NEW 4-STORY TYPE V-A 105 UNIT MIXED-USE APARTMENT BUILDING WITH OFFICE & RESIDENTIAL UNITS AT GROUND FLOOR & OVER ONE LEVEL TYPE I-A SUBTERRANIAN PARKING GARAGE. (PER DIR-2018-1094-SPR).
- Permit Issued
- Issued on 11/23/2020
- Issuing Office
- Current Status
- Permit Finaled on 1/17/2024
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | GARO TELMI |
| Corrections Issued | 2/3/2020 | GARO TELMI |
| Quality Review Completed | 2/5/2020 | KEN GILL |
| Building Plans Picked Up | 2/13/2020 | APPLICANT |
| Applicant returned to address corrections | 4/6/2020 | GARO TELMI |
| Applicant returned to address corrections | 4/29/2020 | GARO TELMI |
| Green Plans Picked Up | 5/8/2020 | APPLICANT |
| Applicant returned to address corrections | 5/12/2020 | GARO TELMI |
| Applicant returned to address corrections | 6/30/2020 | GARO TELMI |
| Applicant returned to address corrections | 7/10/2020 | GARO TELMI |
| Applicant returned to address corrections | 8/20/2020 | GARO TELMI |
| Applicant returned to address corrections | 10/16/2020 | GARO TELMI |
| Plan Check Approved | 11/20/2020 | GARO TELMI |
| Issued | 11/23/2020 | APPLICANT |
| Permit Finaled | 1/16/2024 | JONATHAN HOM |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 5/20/2020 | HELEN JADALI |
| Encroachment in public way | Cleared | 5/26/2020 | ELENA LOPEZ |
| Low Impact Development | Cleared | 7/9/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2020 | ELAINE LEI |
| Construction near power lines | Cleared | 7/21/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/21/2020 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 7/29/2020 | JOHN KIM |
| Excavation more than 5-ft deep | Cleared | 8/13/2020 | CALOSHA APPROVED |
| Metro Rail approval | Cleared | 10/7/2020 | GARO TELMI |
| Work Adjacent to Public Way | Cleared | 10/16/2020 | GARO TELMI |
| "D" conditions | Cleared | 11/4/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 11/5/2020 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | LINDA MARGARET |
| Miscellaneous | Cleared | 11/12/2020 | RICHARD REASER |
| Tract Map conditions | Cleared | 11/12/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 11/17/2020 | LINDA MARGARET |
| Miscellaneous | Cleared | 11/17/2020 | LINDA MARGARET |
Contact Information
| Architect | Banvard,, Navy Francis; Lic. No.: C18051 | 1738 BERKELEY STREET SANTA MONICA, CA 90404 |
| Contractor | Amcal General Contractors Inc; Lic. No.: 460688-B | 30141 AGOURA ROAD STE 100 AGOURA HILLS, CA 91301 |
| Engineer | Berliner,, Neal David; Lic. No.: GE2576 | 4913 MONUMENT ST SIMI VALLEY, CA 93063 |
| Engineer | Blunda,, Abraham Matthew; Lic. No.: S6536 | 1845 W ORANGEWOOD AVE 200 ORANGE, CA 92868 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
| Engineer | Dupont,, Armando Duarte; Lic. No.: L7780 | 411 JENKS CIR CORONA, CA 92880 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 1/11/2021 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 1/12/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 1/12/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 1/13/2021 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 1/14/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 1/14/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 1/15/2021 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 1/19/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 1/19/2021 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 1/19/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 1/20/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 1/22/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 1/27/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/3/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/4/2021 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 2/4/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/5/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/8/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/9/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/10/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 2/11/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 4/21/2021 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 4/22/2021 | Partial Approval | ALEXANDER HELFER |
| Sub-Drain | 5/12/2021 | Partial Approval | ALEXANDER HELFER |
| Sub-Drain | 5/19/2021 | Approved | VASIL MIHALEV |
| Sub-Drain | 6/16/2021 | Approved | VASIL MIHALEV |
| Approved Compaction Report | 6/21/2021 | Partial Inspection | ALEXANDER HELFER |
| Sub-Drain | 7/6/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 9/21/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 9/22/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 9/22/2021 | Approved | ALEXANDER HELFER |
| Sub-Drain | 9/2/2022 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 9/6/2022 | Partial Inspection | MATTHEW JENKINS |
| Fill/Backfill | 9/6/2022 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 9/6/2022 | Partial Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 9/7/2022 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 9/20/2022 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 9/23/2022 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 9/26/2022 | Partial Inspection | MATTHEW JENKINS |
| Rough | 9/30/2022 | Partial Approval | MATTHEW JENKINS |
| Sub-Drain | 10/3/2022 | Partial Approval | MATTHEW JENKINS |
| Fill/Backfill | 10/7/2022 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 10/7/2022 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 10/14/2022 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 10/21/2022 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 10/27/2022 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 1/3/2023 | Conditional Approval | JONATHAN HOM |
| Fill/Backfill | 1/3/2023 | Partial Inspection | JONATHAN HOM |
| Rough | 1/17/2023 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 2/7/2023 | Partial Inspection | JONATHAN HOM |
| Fill/Backfill | 2/7/2023 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 2/7/2023 | Partial Inspection | JONATHAN HOM |
| Sub-Drain | 2/14/2023 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 5/30/2023 | Not Ready for Inspection | ROBERT HUGHES |
| Rough | 5/30/2023 | Partial Approval | ROBERT HUGHES |
| Final | 10/19/2023 | Partial Inspection | JONATHAN HOM |
| Rough | 10/19/2023 | Partial Inspection | JONATHAN HOM |
| Approved Compaction Report | 10/27/2023 | Approved | JONATHAN HOM |
| Final | 1/16/2024 | Permit Finaled | JONATHAN HOM |
| Rough | 1/16/2024 | Approved | JONATHAN HOM |