105 S ST ANDREWS PL 90004
Certificate Information: 105 S ST ANDREWS PL 90004
- Application / Permit
- 19030-10000-08276
- Plan Check / Job No.
- B19LA26757
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- OVER EXCAVATON GRADING FOR NEW 5 STORY APARTMENT BUILDING WITH ONE LEVEL OF BASEMENT PARKING. (19010-10K-05832)
- Permit Issued
- Issued on 3/3/2023
- Issuing Office
- Metro
- Current Status
- Issued on 3/3/2023
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 2/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | KESETE HAREGOT |
| Corrections Issued | 3/16/2020 | KESETE HAREGOT |
| Quality Review Completed | 3/25/2020 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 7/17/2020 | APPLICANT |
| Applicant returned to address corrections | 10/27/2020 | KESETE HAREGOT |
| Plan Check Approved | 6/21/2022 | KESETE HAREGOT |
| No Progress | 6/21/2022 | KESETE HAREGOT |
| Plan Check Approved | 7/27/2022 | KESETE HAREGOT |
| Issued | 3/3/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | RENZ SORIANO |
| Encroachment in public way | Cleared | 1/28/2021 | ELAINE LEI |
| Work Adjacent to Public Way | Cleared | 2/5/2021 | ROSA SILVA |
| Stormwater Pollution Mitigatn | Cleared | 6/14/2022 | TA ANH |
| Building over 3-story or 36-ft | Cleared | 6/21/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Aram Construction Company; Lic. No.: 934479-B | 8500 WILSHIRE BLVD # 509 BEVERLY HILLS, CA 90211 |
| Engineer | Nazemi,, Hassan Steve; Lic. No.: C44100 | 275 CENTENNIAL WAY 205 TUSTIN, CA 92780 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/16/2023 | Not Ready for Inspection | JONATHAN HOM |
| Bottom/Toe | 8/25/2023 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 8/25/2023 | Approved | JONATHAN HOM |
| Excavation | 8/25/2023 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 8/25/2023 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 9/12/2023 | Approved | ALEXANDER HELFER |
| Sub-Drain | 9/12/2023 | Approved | ALEXANDER HELFER |