111 S SOTO ST 90033

Certificate Information: 111 S SOTO ST 90033

Application / Permit
19030-10000-08128
Plan Check / Job No.
B19LA26358
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR PROPOSED MIXED USE W/ BASEMENT GARAGE
Permit Issued
Issued on 12/3/2021
Issuing Office
Metro
Current Status
Permit Finaled on 6/11/2024

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Green Plans Picked Up 12/20/2019 APPLICANT
Disabled Access Plans Picked Up 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 HERNAN ARREOLA
Corrections Issued 1/15/2020 HERNAN ARREOLA
Quality Review Completed 1/30/2020 BILL STUTSMAN
Building Plans Picked Up 2/3/2020 APPLICANT
Applicant returned to address corrections 3/25/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/26/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/16/2021 HERNAN ARREOLA
Applicant returned to address corrections 11/29/2021 HERNAN ARREOLA
Plan Check Approved 12/3/2021 HERNAN ARREOLA
Issued 12/3/2021 APPLICANT
Permit Finaled 6/10/2024 LANNY MERRICK

Permit Application Clearance Information

Haul Route Cleared 12/2/2021 VERONICA LOPEZ

Contact Information

Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Melo,, Edgard Siongco; Lic. No.: C80534 700 S FLOWER ST 1800      LOS ANGELES, CA 90017

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 12/17/2021 Corrections Issued ROBERT HUGHES
Deputy Grading 2/2/2022 Approved ROBERT HUGHES
Deputy Grading 2/3/2022 Approved ROBERT HUGHES
Deputy Grading 2/4/2022 Approved ROBERT HUGHES
Deputy Grading 2/8/2022 Approved ROBERT HUGHES
Deputy Grading 2/15/2022 Approved ROBERT HUGHES
Deputy Grading 2/18/2022 Conditional Approval LANNY MERRICK
Sub-Drain 3/7/2022 Partial Approval LANNY MERRICK
Deputy Grading 3/8/2022 Approved ROBERT HUGHES
Deputy Grading 3/9/2022 Approved ROBERT HUGHES
Sub-Drain 3/9/2022 Partial Approval ROBERT HUGHES
Sub-Drain 3/14/2022 Partial Approval ROBERT HUGHES
Bottom/Toe 5/13/2022 Partial Approval ROBERT HUGHES
Fill/Backfill 5/24/2022 Not Ready for Inspection ROBERT HUGHES
Bottom/Toe 4/17/2024 Partial Inspection LANNY MERRICK
Final 4/17/2024 Not Ready for Inspection LANNY MERRICK
Rough 4/17/2024 Partial Inspection LANNY MERRICK
Drainage Devices/Catch Basin 5/2/2024 Approved LANNY MERRICK
Sub-Drain 5/2/2024 Approved LANNY MERRICK
Approved Compaction Report 5/17/2024 Approved MICHAEL TEMPLE
Special/Order Compliance 5/28/2024 Corrections Issued LANNY MERRICK
Bottom/Toe 6/10/2024 Approved LANNY MERRICK
Final 6/10/2024 Permit Finaled LANNY MERRICK
Rough 6/10/2024 Approved LANNY MERRICK