1 S LMU DR 90045
Certificate Information: 1 S LMU DR 90045
- Application / Permit
- 19030-10000-07516
- Plan Check / Job No.
- B19LA24624
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR NEW 4 STORY, TYPE IIA, SFTV UNDERGRADUATE BUILDING AND LECTURE HALL UNDER PERMIT #19010-10000-03769**
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/10/2022
Permit Application Status History
| Submitted | 11/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | KESETE HAREGOT |
| Corrections Issued | 11/25/2019 | KESETE HAREGOT |
| Quality Review Completed | 11/27/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 11/27/2019 | APPLICANT |
| Plan Check Approved | 1/30/2020 | KESETE HAREGOT |
| Issued | 2/5/2020 | LADBS |
| Permit Finaled-Status Void | 6/14/2021 | MATTHEW JENKINS |
| Re-Activate Permit | 11/5/2021 | MATTHEW JENKINS |
| Permit Finaled | 11/8/2022 | JONATHAN HOM |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 12/10/2019 | CALOSHA APPROVED |
| Specific Plan | Cleared | 1/17/2020 | ESTHER AMAYA |
| Disturb/Remove Protected Trees | Cleared | 1/21/2020 | STEPHEN DUPREY |
| Stormwater Pollution Mitigatn | Cleared | 1/22/2020 | SARAH YOUSSEF |
| GPI Written Notices | Cleared | 1/30/2020 | KESETE HAREGOT |
| Grading Pre-Inspection | Cleared | 1/30/2020 | KESETE HAREGOT |
Contact Information
| Architect | Danna,, Paul Andrews; Lic. No.: C21705 | 8807 HOLLYWOOD HILLS ROAD LOS ANGELES, CA 90046 |
| Contractor | O'Neil W E Construction Co Of California; Lic. No.: 494031-B | 909 N PACIFIC COAST HWY STE 400 EL SEGUNDO, CA 90245 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/4/2020 | Approved | JONATHAN HOM |
| Bottom/Toe | 3/13/2020 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 3/27/2020 | Conditional Approval | JONATHAN HOM |
| Bottom/Toe | 4/3/2020 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 4/13/2020 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 4/17/2020 | Conditional Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 4/22/2020 | Partial Inspection | MATTHEW JENKINS |
| Rough | 4/22/2020 | Partial Inspection | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 4/29/2020 | Partial Approval | KIRK LINKLATER |
| Bottom/Toe | 5/21/2020 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 5/22/2020 | Partial Inspection | MATTHEW JENKINS |
| Rough | 5/22/2020 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 5/22/2020 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 5/28/2020 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 5/29/2020 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 6/2/2020 | Partial Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 6/8/2020 | Partial Approval | KIRK LINKLATER |
| Drainage Devices/Catch Basin | 6/10/2020 | Conditional Approval | MATTHEW JENKINS |
| Drainage Devices/Catch Basin | 7/8/2020 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 6/14/2021 | Approved | MATTHEW JENKINS |
| Final | 6/14/2021 | Partial Inspection | MATTHEW JENKINS |
| Rough | 6/14/2021 | Approved | MATTHEW JENKINS |
| Approved Compaction Report | 11/30/2021 | Approved | JONATHAN HOM |
| Final | 11/8/2022 | Permit Finaled | JONATHAN HOM |
| Special/Order Compliance | 11/8/2022 | Approved | JONATHAN HOM |