668 S ALAMEDA ST 90021

Certificate Information: 668 S ALAMEDA ST 90021

Application / Permit
19030-10000-07209
Plan Check / Job No.
B19LA23755
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
EARLY START GRADING PERMIT : SITE PREPARATION & EXCAVATION (136715 CY ) FOR New mixed use development consisting of 5 1evels of Type IllA residential above 2 level of on grade Type I commercial and parking and 3 levels of Type IA subteranean parking.
Permit Issued
Issued on 10/16/2020
Issuing Office
Metro
Current Status
Permit Finaled on 7/1/2024

Permit Application Status History

Submitted 11/7/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 GARO TELMI
Corrections Issued 11/25/2019 GARO TELMI
Quality Review Completed 11/25/2019 KEN GILL
Building Plans Picked Up 11/27/2019 APPLICANT
Applicant returned to address corrections 4/29/2020 GARO TELMI
Applicant returned to address corrections 7/10/2020 GARO TELMI
Applicant returned to address corrections 9/23/2020 GARO TELMI
Plan Check Approved 9/30/2020 GARO TELMI
Issued 10/16/2020 APPLICANT
Permit Finaled 6/28/2024 LANNY MERRICK

Permit Application Clearance Information

Address approval Cleared 2/7/2020 THOMAS LANG
DAS Clearance Cleared 2/7/2020 GARO TELMI
Green Code Cleared 2/7/2020 GARO TELMI
Highway dedication Cleared 2/7/2020 THOMAS LANG
Sewer availability Cleared 2/7/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/12/2020 THOMAS LANG
Fire Marshall Fire Life Safety Cleared 2/13/2020 ANDREW KO
Encroachment in public way Cleared 4/14/2020 ELAINE LEI
Construction near power lines Cleared 5/8/2020 RIDWAN HARDY
Construction within easement Cleared 5/8/2020 RIDWAN HARDY
Miscellaneous Cleared 5/18/2020 ANNA VIDAL
Low Impact Development Cleared 5/19/2020 ORVAL HERNANDEZ-MARCI
Stormwater Pollution Mitigatn Cleared 5/19/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/29/2020 THOMAS LANG
Senate Bill 35 Cleared 6/17/2020 ERIN STRELICH
Excavation more than 5-ft deep Cleared 6/19/2020 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 6/22/2020 VINCENT QUITORIANO
ZI Cleared 6/22/2020 VINCENT QUITORIANO
"D" conditions Cleared 6/26/2020 ERIN STRELICH
"T" removal Cleared 6/26/2020 ERIN STRELICH
Site Plan review Cleared 6/26/2020 ERIN STRELICH
Bicycle Parking Cleared 7/16/2020 ELENA LOPEZ
Internal circulation Cleared 7/29/2020 TAIMOUR TANAVOLI
Hydrant and Access approval Cleared 8/14/2020 GILBERT URREA
Work Adjacent to Public Way Cleared 9/23/2020 BOK GOH

Contact Information

Contractor Doja Inc; Lic. No.: 597764-C21 5050 W MISSION BLVD      ONTARIO, CA 91762
Engineer Cords,, Donald Alan; Lic. No.: GE2529 3553 TEXAS ST      SAN DIEGO, CA 92104
Engineer Powers,, Brian Frederick; Lic. No.: C75902 2090 WEST 31ST STREET      LOS ANGELES, CA 90018

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/20/2020 Approved ROBERT HUGHES
Deputy Grading 11/12/2020 Approved ROBERT HUGHES
Deputy Grading 11/13/2020 Approved ROBERT HUGHES
Deputy Grading 11/16/2020 Approved ROBERT HUGHES
Deputy Grading 11/17/2020 Approved ROBERT HUGHES
Deputy Grading 11/18/2020 Partial Approval ROBERT HUGHES
Deputy Grading 11/19/2020 Approved ROBERT HUGHES
Deputy Grading 11/20/2020 Approved ROBERT HUGHES
Deputy Grading 2/17/2021 Approved ROBERT HUGHES
Sub-Drain 2/17/2021 Partial Approval ROBERT HUGHES
Deputy Grading 2/18/2021 Approved ROBERT HUGHES
Deputy Grading 2/19/2021 Approved ROBERT HUGHES
Sub-Drain 2/19/2021 Corrections Issued ROBERT HUGHES
Deputy Grading 2/23/2021 Approved ROBERT HUGHES
Sub-Drain 2/23/2021 Partial Approval ROBERT HUGHES
Deputy Grading 2/24/2021 Approved ROBERT HUGHES
Deputy Grading 2/25/2021 Approved ROBERT HUGHES
Sub-Drain 2/25/2021 Partial Approval ROBERT HUGHES
Deputy Grading 2/26/2021 Approved ROBERT HUGHES
Deputy Grading 3/1/2021 Approved ROBERT HUGHES
Deputy Grading 3/2/2021 Approved ALEXANDER HELFER
Deputy Grading 3/3/2021 Approved ALEXANDER HELFER
Sub-Drain 3/3/2021 Partial Approval ALEXANDER HELFER
Deputy Grading 3/4/2021 Approved ALEXANDER HELFER
Deputy Grading 3/5/2021 Approved ALEXANDER HELFER
Deputy Grading 3/8/2021 Approved ROBERT HUGHES
Deputy Grading 3/9/2021 Approved ROBERT HUGHES
Deputy Grading 3/10/2021 Approved ROBERT HUGHES
Deputy Grading 3/11/2021 Approved ROBERT HUGHES
Deputy Grading 3/12/2021 Approved ROBERT HUGHES
Sub-Drain 3/12/2021 Partial Approval ROBERT HUGHES
Deputy Grading 3/15/2021 Approved ROBERT HUGHES
Deputy Grading 3/16/2021 Approved ROBERT HUGHES
Deputy Grading 3/17/2021 Approved ROBERT HUGHES
Sub-Drain 3/17/2021 Not Ready for Inspection ROBERT HUGHES
Deputy Grading 3/19/2021 Approved ROBERT HUGHES
Deputy Grading 3/22/2021 Approved ROBERT HUGHES
Deputy Grading 3/23/2021 Approved ROBERT HUGHES
Sub-Drain 3/23/2021 Partial Approval ROBERT HUGHES
Deputy Grading 3/24/2021 Approved ROBERT HUGHES
Deputy Grading 3/25/2021 Approved ROBERT HUGHES
Deputy Grading 3/26/2021 Approved ROBERT HUGHES
Deputy Grading 4/15/2021 Approved ROBERT HUGHES
Sub-Drain 4/15/2021 Partial Approval ROBERT HUGHES
Sub-Drain 4/20/2021 Partial Approval ROBERT HUGHES
Deputy Grading 5/11/2021 Approved ROBERT HUGHES
Deputy Grading 5/12/2021 Approved ROBERT HUGHES
Sub-Drain 5/12/2021 Partial Approval ROBERT HUGHES
Deputy Grading 5/24/2021 Approved ROBERT HUGHES
Sub-Drain 5/24/2021 Partial Approval ROBERT HUGHES
Bottom/Toe 8/17/2021 Partial Approval ROBERT HUGHES
Fill/Backfill 1/25/2022 Partial Approval LANNY MERRICK
Fill/Backfill 2/7/2022 Partial Approval LANNY MERRICK
Fill/Backfill 2/14/2022 Partial Inspection LANNY MERRICK
Sub-Drain 2/24/2022 Partial Approval LANNY MERRICK
Approved Compaction Report 3/1/2022 Not Ready for Inspection LANNY MERRICK
Private Sewage Disposal System 3/1/2022 Partial Inspection LANNY MERRICK
Drainage Devices/Catch Basin 3/11/2022 Not Ready for Inspection LANNY MERRICK
Fill/Backfill 3/17/2022 Not Ready for Inspection LANNY MERRICK
Fill/Backfill 3/21/2022 Partial Approval LANNY MERRICK
Fill/Backfill 4/1/2022 Partial Approval LANNY MERRICK
Fill/Backfill 4/4/2022 Partial Approval LANNY MERRICK
Sub-Drain 4/11/2022 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 4/15/2022 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 4/27/2022 Partial Approval ROBERT HUGHES
Sub-Drain 5/9/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 5/11/2022 Partial Approval ROBERT HUGHES
Sub-Drain 5/19/2022 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 6/16/2022 Partial Approval ROBERT HUGHES
Sub-Drain 8/10/2022 Partial Approval MATTHEW JENKINS
Drainage Devices/Catch Basin 8/15/2022 Partial Approval ROBERT HUGHES
Sub-Drain 8/22/2022 Partial Approval LANNY MERRICK
Sub-Drain 9/1/2022 Partial Approval MATTHEW JENKINS
Drainage Devices/Catch Basin 9/19/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/3/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/4/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/7/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/13/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/18/2022 Partial Approval ROBERT HUGHES
Sub-Drain 10/24/2022 Partial Approval KIRK LINKLATER
Drainage Devices/Catch Basin 10/26/2022 Partial Approval ROBERT HUGHES
Drainage Devices/Catch Basin 10/27/2022 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 11/1/2022 Partial Approval ROBERT HUGHES
Sub-Drain 11/2/2022 Not Ready for Inspection ROBERT HUGHES
Drainage Devices/Catch Basin 2/16/2023 Not Ready for Inspection LANNY MERRICK
Sub-Drain 6/16/2023 Conditional Approval JONATHAN HOM
Bottom/Toe 3/14/2024 Not Ready for Inspection LANNY MERRICK
Final 3/14/2024 Not Ready for Inspection LANNY MERRICK
Rough 3/14/2024 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 3/21/2024 Not Ready for Inspection LANNY MERRICK
Final 3/21/2024 Not Ready for Inspection LANNY MERRICK
Rough 3/21/2024 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 6/28/2024 Approved LANNY MERRICK
Final 6/28/2024 Permit Finaled LANNY MERRICK
Rough 6/28/2024 Approved LANNY MERRICK