546 N HARVARD BLVD 1-9 90004
Certificate Information: 546 N HARVARD BLVD 1-9 90004
- Application / Permit
- 19030-10000-07085
- Plan Check / Job No.
- B18LA12148
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading for 3 Story Apartment Building with 1 Story Basement.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/14/2023
Permit Application Status History
| Submitted | 6/15/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 8/3/2018 | APPLICANT |
| Green Plans Picked Up | 8/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2018 | DINA ELKINAWY |
| Corrections Issued | 8/22/2018 | DINA ELKINAWY |
| Quality Review Completed | 8/24/2018 | DAVID CHANG |
| Building Plans Picked Up | 8/24/2018 | APPLICANT |
| Applicant returned to address corrections | 9/26/2018 | DINA ELKINAWY |
| Applicant returned to address corrections | 3/6/2019 | DINA ELKINAWY |
| Applicant returned to address corrections | 11/1/2019 | DINA ELKINAWY |
| Applicant returned to address corrections | 11/15/2019 | DINA ELKINAWY |
| Plan Check Approved | 12/3/2019 | DINA ELKINAWY |
| Issued | 7/17/2020 | APPLICANT |
| Permit Finaled | 12/13/2023 | ALEXANDER HELFER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Chiang, Architects; Lic. No.: C36400 | 27956 PERIWINKLE LANE VALENCIA, CA 91354 |
| Contractor | Sanders Construction Company; Lic. No.: 588917-B | 24307 MAGIC MOUNTAIN PARKWAY #107 VALENCIA, CA 91355 |
| Engineer | Phan, Phillip Trung Tri; Lic. No.: C76425 | 19221 E NORTHAM WEST COVINA, CA 91792 |
Inspector Information
| LANNY MERRICK, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/17/2020 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 9/21/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Sub-Drain | 10/20/2020 | Approved | ALEXANDER HELFER |
| Sub-Drain | 3/26/2021 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 6/2/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Fill/Backfill | 7/26/2021 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 7/26/2021 | Partial Approval | ROBERT HUGHES |
| Approved Compaction Report | 11/21/2022 | Approved | ROBERT HUGHES |
| Bottom/Toe | 12/13/2023 | Approved | ALEXANDER HELFER |
| Final | 12/13/2023 | Permit Finaled | ALEXANDER HELFER |