642 N SAINT CLOUD ROAD 90077
Certificate Information: 642 N SAINT CLOUD ROAD 90077
- Application / Permit
- 19030-10000-06937
- Plan Check / Job No.
- B19LA22293
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- EXCAVAYION & BACK FILL FOR NEW 14' X 41'X 18' WATER CISTERN TANK. (TOTAL 375 C.Y.). .
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/7/2022
Permit Application Status History
| Submitted | 10/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | GARO TELMI |
| Corrections Issued | 10/29/2019 | GARO TELMI |
| Quality Review Completed | 10/30/2019 | KEN GILL |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Applicant returned to address corrections | 1/24/2020 | GARO TELMI |
| Plan Check Approved | 2/26/2020 | GARO TELMI |
| Issued | 3/4/2020 | LADBS |
| Refund Closed | 4/6/2020 | MARY SUM |
| Reactivate - Status Void | 4/6/2020 | MARY SUM |
| Refund in Progress-Status Void | 7/30/2020 | CHRISTINA TABIRARA |
| Re-Activate Permit | 8/27/2020 | MARY SUM |
| Permit Finaled | 1/6/2022 | CHARLES POWELL |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/28/2020 | ORVAL HERNANDEZ-MARCI |
| Excavation more than 5-ft deep | Cleared | 2/26/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | G3 Group La Inc; Lic. No.: 989306-B | 2500 TOWNSGATE ROAD SUITE F WESTLAKE VILLAGE, CA 91361 |
| Engineer | Salter,, David R; Lic. No.: C69911 | 3445 CEDAR ST SANTA YNEZ, CA 93460 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Byer,, John W; Lic. No.: EG883 | 1649 PUEBLA DRIVE GLENDALE, CA 91207 |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 4/27/2020 | Approved | BRIAN OLSON |
| Bottom/Toe | 8/28/2020 | Partial Approval | BRIAN OLSON |
| Drainage Devices/Catch Basin | 11/25/2020 | Partial Inspection | BRIAN OLSON |
| Bottom/Toe | 1/6/2022 | Approved | CHARLES POWELL |
| Final | 1/6/2022 | Permit Finaled | CHARLES POWELL |
| Rough | 1/6/2022 | Approved | CHARLES POWELL |