11145 N WOODLEY AVE 91344
Certificate Information: 11145 N WOODLEY AVE 91344
- Application / Permit
- 19030-10000-05929
- Plan Check / Job No.
- B19LA19491
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- ROUGH AND PRECISE GRADING FOR: 2 LEVELS OF TYPE V-A WOOD FRAMED APARTMENTS OVER 1 LEVEL OF TYPE 1-A CONCRETE COMMERCIAL OFFICE AND PARKING, 80 UNITS, 3-STORIES. (3,000CY) BF 210046 APPROVED FOR AN EXPORT OF 25,000 CUBIC YARDS
- Permit Issued
- Issued on 9/14/2022
- Issuing Office
- Current Status
- Issued on 9/14/2022
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | JOE VO |
| Plans on Hold | 9/26/2019 | SIAVOSH POURSABAHIAN |
| Hold Released | 10/7/2019 | SIAVOSH POURSABAHIAN |
| Corrections Issued | 10/22/2019 | JOE VO |
| Disabled Access Plans Picked Up | 10/30/2019 | APPLICANT |
| Quality Review Completed | 11/14/2019 | KEN GILL |
| Applicant returned to address corrections | 11/17/2020 | JOE VO |
| Applicant returned to address corrections | 12/3/2020 | JOE VO |
| Green Plans Picked Up | 12/24/2020 | APPLICANT |
| Applicant returned to address corrections | 10/25/2021 | JOE VO |
| Applicant returned to address corrections | 10/26/2021 | JOE VO |
| Applicant returned to address corrections | 2/7/2022 | JOE VO |
| Plan Check Approved | 7/18/2022 | JOE VO |
| Issued | 9/14/2022 | APPLICANT |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
Permit Application Clearance Information
| Haul Route | Cleared | 6/14/2022 | VERONICA LOPEZ |
Contact Information
| Contractor | Hillcrest Construction Group Llc; Lic. No.: 1086392-B | 1875 CENTURY PARK EAST SUITE 1130 LOS ANGELES, CA 90067 |
Inspector Information
| ALEXANDER HELFER, (818) 374-4354 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 8/7/2023 | Approved | BRIAN MILLER |
| Initial Grading | 11/7/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 11/13/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 11/14/2023 | No Access for Inspection | VASIL MIHALEV |
| Deputy Grading | 11/15/2023 | No Access for Inspection | VASIL MIHALEV |
| Deputy Grading | 11/16/2023 | Approved | ALEXANDER HELFER |
| Deputy Grading | 11/17/2023 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Grading | 11/20/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 11/21/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 11/22/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 11/28/2023 | Approved | ROBERT PINA |
| Deputy Grading | 11/29/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 11/30/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 12/1/2023 | Approved | BRIAN MILLER |
| Bottom/Toe | 12/12/2023 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 5/16/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 9/12/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 9/23/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 9/30/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 10/22/2025 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 11/4/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 11/6/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 11/13/2025 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 12/5/2025 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 1/23/2026 | Approved | ALEXANDER HELFER |
| Final | 1/23/2026 | Corrections Issued | ALEXANDER HELFER |
| Rough | 1/23/2026 | Approved | ALEXANDER HELFER |