2528 S GRAND AVE 90007

Certificate Information: 2528 S GRAND AVE 90007

Application / Permit
19030-10000-05782
Plan Check / Job No.
B19LA18998
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
Site Grading.
Permit Issued
Issued on 12/21/2020
Issuing Office
Current Status
Permit Finaled on 7/3/2023

Permit Application Status History

Submitted 9/23/2019 APPLICANT
Assigned to Plan Check Engineer 9/23/2019 SALVADOR QUINTANILLA
Corrections Issued 9/23/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 11/7/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 4/2/2020 SALVADOR QUINTANILLA
Plan Check Approved 12/17/2020 SALVADOR QUINTANILLA
Issued 12/21/2020 APPLICANT
Permit Finaled 7/3/2023 ROBERT HUGHES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2020 LEE GUILBEAUX
Community Plan Implem. Overlay Cleared 6/2/2020 HELEN JADALI
Excavation more than 5-ft deep Cleared 8/12/2020 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 10/2/2020 ROSA SILVA
Project located in CRA area Cleared 10/22/2020 GRACIELA ACOSTA
Redevelopment Project Area Cleared 10/22/2020 GRACIELA ACOSTA

Contact Information

Contractor Wpic Construction Llc; Lic. No.: 1029691-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/13/2021 Corrections Issued ALEXANDER HELFER
Bottom/Toe 1/25/2021 Partial Approval ALEXANDER HELFER
Deputy Grading 1/25/2021 Approved ALEXANDER HELFER
Bottom/Toe 1/26/2021 Partial Approval ALEXANDER HELFER
Deputy Grading 1/27/2021 Approved VASIL MIHALEV
Bottom/Toe 1/28/2021 Approved VASIL MIHALEV
Deputy Grading 1/28/2021 Approved VASIL MIHALEV
Deputy Grading 1/29/2021 Approved VASIL MIHALEV
Deputy Grading 2/3/2021 Approved ALEXANDER HELFER
Deputy Grading 2/4/2021 Approved ALEXANDER HELFER
Deputy Grading 2/5/2021 Approved ALEXANDER HELFER
Excavation 2/5/2021 Approved ALEXANDER HELFER
Deputy Grading 2/9/2021 Approved ALEXANDER HELFER
Bottom/Toe 2/10/2021 Partial Approval ALEXANDER HELFER
Deputy Grading 2/10/2021 Approved ALEXANDER HELFER
Bottom/Toe 2/18/2021 Partial Approval ALEXANDER HELFER
Deputy Grading 2/18/2021 Approved ALEXANDER HELFER
Fill/Backfill 2/18/2021 Partial Approval ALEXANDER HELFER
Approved Compaction Report 2/23/2021 Approved ALEXANDER HELFER
Approved Compaction Report 3/8/2021 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 9/7/2022 Not Ready for Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 9/9/2022 Partial Inspection MATTHEW JENKINS
Special/Order Compliance 9/9/2022 Partial Inspection MATTHEW JENKINS
Bottom/Toe 5/25/2023 Partial Inspection JONATHAN HOM
Rough 5/25/2023 Not Ready for Inspection JONATHAN HOM
Final 5/30/2023 Not Ready for Inspection ROBERT HUGHES
Approved Compaction Report 6/2/2023 Approved ALEXANDER HELFER
Bottom/Toe 7/3/2023 Approved ROBERT HUGHES
Final 7/3/2023 Permit Finaled ROBERT HUGHES
Rough 7/3/2023 Approved ROBERT HUGHES