1414 S BEVERLY DR 90035
Certificate Information: 1414 S BEVERLY DR 90035
- Application / Permit
- 19030-10000-05460
- Plan Check / Job No.
- B19LA17910
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR PROPOSED 4 STORY 10 UNIT APARTMENT OVER SUB. GARAGE & ROOF DECK 2 OF 2 BF 190116 APPROVED FOR AN EXPORT OF 2,250 CUBIC YARDS
- Permit Issued
- Issued on 8/17/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/26/2025
Permit Application Status History
| Submitted | 8/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | VU NGUYEN |
| Corrections Issued | 9/30/2019 | VU NGUYEN |
| Quality Review Completed | 11/5/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 1/21/2020 | VU NGUYEN |
| Applicant returned to address corrections | 1/31/2020 | VU NGUYEN |
| Applicant returned to address corrections | 2/12/2020 | VU NGUYEN |
| Applicant returned to address corrections | 3/3/2020 | VU NGUYEN |
| Plan Check Approved | 6/16/2020 | VU NGUYEN |
| Green Plans Picked Up | 3/15/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 10/27/2021 | APPLICANT |
| Plan Check Approved | 3/8/2022 | VU NGUYEN |
| Issued | 8/17/2022 | APPLICANT |
| Permit Finaled | 8/25/2025 | LANNY MERRICK |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 1/31/2020 | CALOSHA APPROVED |
| "Q" conditions | Cleared | 2/12/2020 | SARAHI ORTEGA |
| Construction near power lines | Cleared | 2/12/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2020 | ERIK BEASLEY |
| Low Impact Development | Cleared | 2/12/2020 | MITESH PATEL |
| Work Adjacent to Public Way | Cleared | 2/13/2020 | JENNY CEA |
| Trees in Parkway | Cleared | 2/19/2020 | ADRIAN SANCHEZ |
| Haul Route | Cleared | 2/21/2020 | VERONICA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 4/24/2023 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 4/24/2023 | Partial Approval | MATTHEW JENKINS |
| Excavation | 5/9/2023 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 5/9/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 6/6/2023 | Partial Inspection | MATTHEW JENKINS |
| Sub-Drain | 6/6/2023 | Conditional Approval | MATTHEW JENKINS |
| Bottom/Toe | 7/8/2025 | Not Ready for Inspection | AL GAMBLE |
| Final | 7/8/2025 | Not Ready for Inspection | AL GAMBLE |
| Rough | 7/8/2025 | Not Ready for Inspection | AL GAMBLE |
| Approved Compaction Report | 7/24/2025 | Approved | MATTHEW JENKINS |
| Bottom/Toe | 8/25/2025 | Approved | LANNY MERRICK |
| Final | 8/25/2025 | Permit Finaled | LANNY MERRICK |
| Rough | 8/25/2025 | Approved | LANNY MERRICK |