3191 N TOPPINGTON DR 90210
Certificate Information: 3191 N TOPPINGTON DR 90210
- Application / Permit
- 19030-10000-04550
- Plan Check / Job No.
- B19LA14706
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR ADDITION TO 2-STORY SINGLE FAMILY RESIDENCE
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/25/2025
Permit Application Status History
| Submitted | 7/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | VU NGUYEN |
| Corrections Issued | 8/27/2019 | VU NGUYEN |
| Green Plans Picked Up | 9/6/2019 | APPLICANT |
| Quality Review Completed | 9/16/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Applicant returned to address corrections | 1/14/2020 | VU NGUYEN |
| Applicant returned to address corrections | 1/30/2020 | VU NGUYEN |
| Applicant returned to address corrections | 3/2/2020 | VU NGUYEN |
| Applicant returned to address corrections | 3/10/2020 | VU NGUYEN |
| Plan Check Approved | 3/17/2020 | VU NGUYEN |
| Issued | 11/4/2021 | APPLICANT |
| Permit Finaled | 2/25/2025 | ALEXANDER HELFER |
Permit Application Clearance Information
| Disturb/Remove Protected Trees | Cleared | 10/9/2019 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | DINAH GARIN |
| Miscellaneous | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Specific Plan | Cleared | 12/12/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 12/12/2019 | SARAH GOLDMAN |
| Construction near power lines | Cleared | 12/13/2019 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 1/30/2020 | ORVAL HERNANDEZ-MARCIAL |
| Excavation more than 5-ft deep | Cleared | 3/10/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 3/17/2020 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 3/17/2020 | VU NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
| Geologist | Haney,, Harry Drew; Lic. No.: EG2091 | 9003 DE SOTO AVENUE CANOGA PARK, CA 91304 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 2/2/2022 | Corrections Issued | ALEXANDER HELFER |
| Bottom/Toe | 3/23/2022 | Partial Approval | ALEXANDER HELFER |
| Bottom/Toe | 4/1/2022 | Partial Approval | ALEXANDER HELFER |
| Approved Compaction Report | 5/17/2022 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 8/25/2023 | Partial Approval | ALEXANDER HELFER |
| Bottom/Toe | 1/23/2025 | Corrections Issued | ALEXANDER HELFER |
| Final | 1/23/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 1/23/2025 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 2/7/2025 | Approved | MICHAEL TEMPLE |
| Final | 2/24/2025 | Partial Inspection | ALEXANDER HELFER |
| Bottom/Toe | 2/25/2025 | Approved | ALEXANDER HELFER |
| Final | 2/25/2025 | Permit Finaled | ALEXANDER HELFER |