1537 S WILTON PL 90019

Certificate Information: 1537 S WILTON PL 90019

Application / Permit
19030-10000-04410
Plan Check / Job No.
B19LA14241
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(60) Grading - Non-Hillside
Work Description
EXCAVATION FOR NEW APARTMENT BUILDING WITH SUB PARKING.
Permit Issued
Issued on 2/7/2023
Issuing Office
Metro
Current Status
Permit Finaled on 5/6/2025

Permit Application Status History

Submitted 7/11/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 MICHAEL PEREZ
Corrections Issued 8/13/2019 MICHAEL PEREZ
Building Plans Picked Up 8/29/2019 APPLICANT
Quality Review Completed 8/30/2019 JOSE RODRIGUEZ
Plan Check Approved 2/3/2023 DANIEL YIP
Issued 2/7/2023 APPLICANT
Permit Finaled 5/6/2025 MICHAEL TEMPLE

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 2/1/2023 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/1/2023 MICHAEL PEREZ
Community Plan Implem. Overlay Cleared 2/2/2023 RAFAEL FONTES

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Owner-Builder       ,
Engineer Eftekhari,, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 2/8/2023 Partial Inspection JONATHAN HOM
Excavation 2/8/2023 Partial Inspection JONATHAN HOM
Initial Grading 2/8/2023 Partial Inspection JONATHAN HOM
Sub-Drain 2/8/2023 Partial Approval JONATHAN HOM
Bottom/Toe 12/31/2024 Not Ready for Inspection JONATHAN HOM
Final 12/31/2024 Not Ready for Inspection JONATHAN HOM
Rough 12/31/2024 Not Ready for Inspection JONATHAN HOM
Final 4/10/2025 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 4/15/2025 Approved JONATHAN HOM
Final 4/15/2025 Partial Approval JONATHAN HOM
Rough 4/15/2025 Approved JONATHAN HOM
Approved Compaction Report 5/6/2025 Approved MICHAEL TEMPLE
Final 5/6/2025 Permit Finaled MICHAEL TEMPLE