2657 N LARMAR ROAD 90068
Certificate Information: 2657 N LARMAR ROAD 90068
- Application / Permit
- 19030-10000-03755
- Plan Check / Job No.
- B19LA12134
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING OF NEW SFD W/ BASEMENT AND NEW RETAINING WALL CUT:688 C.Y FILL:115 C.Y TOTAL GRADING:803 C.Y IMPORT:0 C.Y EXPORT:583 C.Y
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/1/2024
Permit Application Status History
| Submitted | 6/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | JESSE VIDUYA |
| Corrections Issued | 7/2/2019 | JEFFREY MACHADO |
| Quality Review Completed | 7/20/2019 | STANLEY RAAP |
| Building Plans Picked Up | 7/31/2019 | APPLICANT |
| Applicant returned to address corrections | 12/10/2019 | JESSE VIDUYA |
| Green Plans Picked Up | 12/11/2019 | APPLICANT |
| Applicant returned to address corrections | 2/20/2020 | JESSE VIDUYA |
| Plan Check Approved | 4/9/2020 | JESSE VIDUYA |
| Issued | 7/14/2020 | APPLICANT |
| Permit Finaled | 10/31/2024 | ALEXANDER HELFER |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/21/2019 | SOPHIE GABEL-SCHEINBAU |
| Specific Plan | Cleared | 8/21/2019 | SOPHIE GABEL-SCHEINBAU |
| GPI Written Notices | Cleared | 4/6/2020 | JEFFREY MACHADO |
| Grading Pre-Inspection | Cleared | 4/6/2020 | JESSE VIDUYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Larocca,, Francis Joseph; Lic. No.: C75121 | 1821 PACIFIC COAST HWY 38 HERMOSA BEACH, CA 90254 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/22/2020 | Corrections Issued | VASIL MIHALEV |
| Excavation | 8/5/2020 | Partial Inspection | ALEXANDER HELFER |
| Bottom/Toe | 8/11/2020 | Not Ready for Inspection | VASIL MIHALEV |
| Sub-Drain | 9/18/2020 | Approved | VASIL MIHALEV |
| Sub-Drain | 10/22/2020 | Approved | VASIL MIHALEV |
| Approved Compaction Report | 10/30/2020 | Not Ready for Inspection | VASIL MIHALEV |
| Fill/Backfill | 10/30/2020 | Approved | VASIL MIHALEV |
| Initial Grading | 3/5/2021 | Conditional Approval | VASIL MIHALEV |
| Bottom/Toe | 3/8/2021 | Approved | VASIL MIHALEV |
| Excavation | 3/22/2021 | Approved | VASIL MIHALEV |
| Excavation | 3/24/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation | 3/25/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation | 3/26/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Fill/Backfill | 7/20/2021 | Approved | ALEXANDER HELFER |
| Private Sewage Disposal System | 7/20/2021 | Not Ready for Inspection | ALEXANDER HELFER |
| Sub-Drain | 7/20/2021 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 2/7/2022 | Partial Inspection | ALEXANDER HELFER |
| Irrigation/Landscape | 2/7/2022 | Partial Inspection | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/26/2022 | Partial Inspection | MATTHEW JENKINS |
| Approved Compaction Report | 10/16/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Final | 10/16/2024 | Not Ready for Inspection | ALEXANDER HELFER |
| Rough | 10/16/2024 | Approved | ALEXANDER HELFER |
| Sub-Drain | 10/16/2024 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 10/21/2024 | Approved | ALEXANDER HELFER |
| Final | 10/31/2024 | Permit Finaled | ALEXANDER HELFER |