1157 S HOOVER ST 90006
Certificate Information: 1157 S HOOVER ST 90006
- Application / Permit
- 19030-10000-02759
- Plan Check / Job No.
- B19LA08867
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE PREP FOR APARMENT AND RETAINING WALL BACKFILL
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/14/2023
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | HERNAN ARREOLA |
| Corrections Issued | 7/1/2019 | HERNAN ARREOLA |
| Quality Review Completed | 7/1/2019 | SIAVOSH POURSABAHIAN |
| Disabled Access Plans Picked Up | 9/11/2019 | APPLICANT |
| Applicant returned to address corrections | 2/26/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/3/2020 | HERNAN ARREOLA |
| Green Plans Picked Up | 10/19/2020 | APPLICANT |
| Applicant returned to address corrections | 11/20/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/18/2021 | HERNAN ARREOLA |
| Plan Check Approved | 7/26/2021 | HERNAN ARREOLA |
| Issued | 7/27/2021 | APPLICANT |
| Building Plans Picked Up | 7/28/2021 | APPLICANT |
| Permit Finaled | 4/13/2023 | JONATHAN HOM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | WALLIE JONG |
Contact Information
| Architect | Afari,, Frank; Lic. No.: C19872 | 1453 CLUBVIEW DRIVE LOS ANGELES, CA 90024 |
| Contractor | Category Construction Llc; Lic. No.: 1041679-B | 8271 MELROSE AVE #207 LOS ANGELES, CA 90046 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Soleymani,, Habib K; Lic. No.: S2575 | 1917 PARNELL AVE LOS ANGELES, CA 90025 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/28/2021 | Approved | ALEXANDER HELFER |
| Excavation | 8/9/2021 | Approved | ALEXANDER HELFER |
| Excavation | 8/16/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/24/2021 | Approved | ALEXANDER HELFER |
| Excavation | 8/24/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Grading | 8/25/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 8/26/2021 | Approved | VASIL MIHALEV |
| Excavation | 8/26/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Deputy Grading | 8/27/2021 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/30/2021 | Approved | ALEXANDER HELFER |
| Excavation | 8/30/2021 | Approved | ALEXANDER HELFER |
| Deputy Grading | 8/31/2021 | Approved | ALEXANDER HELFER |
| Excavation | 9/1/2021 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 9/28/2021 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 3/21/2022 | Not Ready for Inspection | LANNY MERRICK |
| Final | 3/21/2022 | Not Ready for Inspection | LANNY MERRICK |
| Rough | 3/21/2022 | Not Ready for Inspection | LANNY MERRICK |
| Bottom/Toe | 3/7/2023 | Not Ready for Inspection | JONATHAN HOM |
| Final | 3/7/2023 | Partial Inspection | JONATHAN HOM |
| Irrigation/Landscape | 3/7/2023 | Not Ready for Inspection | JONATHAN HOM |
| Rough | 3/7/2023 | Not Ready for Inspection | JONATHAN HOM |
| Bottom/Toe | 4/13/2023 | Approved | JONATHAN HOM |
| Final | 4/13/2023 | Permit Finaled | JONATHAN HOM |
| Rough | 4/13/2023 | Approved | JONATHAN HOM |