6044 E LA PRADA 90042
Certificate Information: 6044 E LA PRADA 90042
- Application / Permit
- 19030-10000-02150
- Plan Check / Job No.
- B19LA04855
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- Grading for retaining wall backfill and site grading
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/19/2020
Permit Application Status History
| Submitted | 3/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | VU NGUYEN |
| Corrections Issued | 4/9/2019 | VU NGUYEN |
| Quality Review Completed | 4/15/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 4/16/2019 | APPLICANT |
| Plan Check Approved | 12/10/2019 | VU NGUYEN |
| Issued | 1/10/2020 | LADBS |
| Permit Finaled | 11/19/2020 | ROBERT HUGHES |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 12/10/2019 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 12/10/2019 | VU NGUYEN |
Contact Information
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Geologist | Minas,, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 1/13/2020 | Approved | TODD MALAND |
| Bottom/Toe | 1/21/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 1/22/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 1/23/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 1/31/2020 | Partial Approval | ROBERT HUGHES |
| Fill/Backfill | 2/3/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 2/7/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Special/Order Compliance | 2/14/2020 | Not Ready for Inspection | ROBERT HUGHES |
| Approved Compaction Report | 2/25/2020 | Approved | ROBERT HUGHES |
| Sub-Drain | 4/2/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 4/3/2020 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 5/5/2020 | Partial Approval | ROBERT HUGHES |
| Drainage Devices/Catch Basin | 5/15/2020 | Partial Approval | ROBERT HUGHES |
| Bottom/Toe | 11/19/2020 | Approved | ROBERT HUGHES |
| Final | 11/19/2020 | Permit Finaled | ROBERT HUGHES |
| Rough | 11/19/2020 | Approved | ROBERT HUGHES |