3320 W 50TH ST 90043

Certificate Information: 3320 W 50TH ST 90043

Application / Permit
19030-10000-00939
Plan Check / Job No.
B19LA03153
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(60) Grading - Non-Hillside
Work Description
Site grading and backfill for retaining wall and built-up platform.
Permit Issued
Issued on 9/1/2023
Issuing Office
Metro
Current Status
Issued on 9/1/2023

Permit Application Status History

Submitted 2/15/2019 APPLICANT
Assigned to Plan Check Engineer 2/27/2019 RODOLFO ARIAS
Corrections Issued 3/1/2019 RODOLFO ARIAS
Building Plans Picked Up 3/1/2019 APPLICANT
Disabled Access Plans Picked Up 3/1/2019 APPLICANT
Quality Review Completed 6/26/2019 MINYE PAK
Applicant returned to address corrections 5/13/2020 RODOLFO ARIAS
Applicant returned to address corrections 7/15/2021 RODOLFO ARIAS
Applicant returned to address corrections 4/13/2022 RODOLFO ARIAS
Applicant returned to address corrections 7/21/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/2/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/9/2022 RODOLFO ARIAS
Applicant returned to address corrections 8/22/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/20/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/21/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/27/2022 RODOLFO ARIAS
Applicant returned to address corrections 9/29/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/14/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/27/2022 RODOLFO ARIAS
Applicant returned to address corrections 12/29/2022 RODOLFO ARIAS
Applicant returned to address corrections 1/5/2023 RODOLFO ARIAS
Applicant returned to address corrections 3/21/2023 RODOLFO ARIAS
Plan Check Approved 3/21/2023 RODOLFO ARIAS
Issued 9/1/2023 APPLICANT

Permit Application Clearance Information

Metro Rail approval Cleared 7/15/2021 EDDI ZEPEDA
Construction near power lines Cleared 8/2/2021 RIDWAN HARDY
ZI Cleared 8/27/2021 TERRI OSBORNE
"D" conditions Cleared 9/2/2021 KYLE WINSTON
CPC Cleared 9/2/2021 KYLE WINSTON
Specific Plan Cleared 9/2/2021 KYLE WINSTON
Trees in Parkway Cleared 1/5/2022 ADALBERTO VERA
Sewer availability Cleared 3/30/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/21/2022 STEVE MELGAR
Historic Resource Verification Cleared 6/6/2022 SUSAN WONG
Redevelopment Project Area Cleared 6/6/2022 SUSAN WONG
Excavation more than 5-ft deep Cleared 9/27/2022 CALOSHA APPROVED
Low Impact Development Cleared 11/8/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/17/2022 STEVE MELGAR
Prkng lot landscape/Water mgmt Cleared 12/15/2022 JAZMIN ROQUE
Work Adjacent to Public Way Cleared 3/9/2023 KHOUNG LE

Contact Information

Architect Bullock,, Gabrielle A; Lic. No.: C30192 242 N LUCERNE BLVD      LOS ANGELES, CA 90004
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 1212 ABBOT KINNEY BLVD #A      LOS ANGELES, CA 90291
Engineer Delgadillo,, Christian; Lic. No.: GE3144 10828 CORD AVE      DOWNEY, CA 90241
Engineer Powers,, Brian Frederick; Lic. No.: C75902 2090 WEST 31ST STREET      LOS ANGELES, CA 90018
Engineer Reynolds,, Aaron D'Angelo; Lic. No.: S4338 4022 JOELTON DRIVE      AGOURA HILLS, CA 91301
Engineer Shimizu,, Ryan Kenji; Lic. No.: C86518 1011 ROSE GLEN AVE      ROSEMEAD, CA 91770

Inspector Information

AL GAMBLE, (213) 482-0403 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/9/2024 Not Ready for Inspection JONATHAN HOM
Excavation 1/10/2024 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 1/11/2024 Partial Inspection JONATHAN HOM
Excavation 1/11/2024 Not Ready for Inspection JONATHAN HOM
Initial Grading 1/12/2024 Partial Approval JONATHAN HOM
Initial Grading 1/26/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 1/29/2024 No Access for Inspection JONATHAN HOM
Initial Grading 1/29/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 1/30/2024 Approved JONATHAN HOM
Excavation 1/30/2024 Conditional Approval JONATHAN HOM
Bottom/Toe 1/31/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 1/31/2024 Approved JONATHAN HOM
Deputy Grading 2/1/2024 No Access for Inspection JONATHAN HOM
Deputy Grading 2/2/2024 No Access for Inspection JONATHAN HOM
Deputy Grading 2/12/2024 Approved JONATHAN HOM
Excavation 2/12/2024 Partial Inspection JONATHAN HOM
Bottom/Toe 2/13/2024 Partial Inspection JONATHAN HOM
Deputy Grading 2/13/2024 Approved JONATHAN HOM
Deputy Grading 2/14/2024 Approved JONATHAN HOM
Deputy Grading 2/15/2024 Approved JONATHAN HOM
Deputy Grading 2/16/2024 Approved JONATHAN HOM
Deputy Grading 2/26/2024 Approved JONATHAN HOM
Bottom/Toe 2/27/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 2/27/2024 Approved JONATHAN HOM
Deputy Grading 2/28/2024 Approved JONATHAN HOM
Rough 2/28/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 2/29/2024 No Access for Inspection JONATHAN HOM
Deputy Grading 3/1/2024 No Access for Inspection JONATHAN HOM
Deputy Grading 3/5/2024 Approved JONATHAN HOM
Deputy Grading 3/6/2024 No Access for Inspection JONATHAN HOM
Deputy Grading 3/7/2024 Approved JONATHAN HOM
Deputy Grading 3/8/2024 Approved JONATHAN HOM
Deputy Grading 3/11/2024 Conditional Approval LANNY MERRICK
Deputy Grading 3/12/2024 Approved JONATHAN HOM
Deputy Grading 3/13/2024 Approved JONATHAN HOM
Deputy Grading 3/14/2024 Approved JONATHAN HOM
Deputy Grading 3/15/2024 No Access for Inspection JONATHAN HOM
Deputy Grading 3/19/2024 Approved JONATHAN HOM
Deputy Grading 3/20/2024 Approved JONATHAN HOM
Deputy Grading 3/21/2024 Approved JONATHAN HOM
Bottom/Toe 3/22/2024 Partial Inspection JONATHAN HOM
Deputy Grading 3/22/2024 Approved JONATHAN HOM
Excavation 3/22/2024 Partial Inspection JONATHAN HOM
Initial Grading 3/22/2024 Partial Inspection JONATHAN HOM
Rough 3/22/2024 Partial Inspection JONATHAN HOM
Excavation 3/26/2024 Not Ready for Inspection MATTHEW JENKINS
Deputy Grading 3/27/2024 Approved JONATHAN HOM
Fill/Backfill 3/27/2024 Partial Inspection JONATHAN HOM
Deputy Grading 3/28/2024 Approved JONATHAN HOM
Deputy Grading 3/29/2024 Approved JONATHAN HOM
Excavation 4/2/2024 Partial Inspection LANNY MERRICK
Bottom/Toe 4/3/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 4/3/2024 Conditional Approval JONATHAN HOM
Deputy Grading 4/4/2024 Approved JONATHAN HOM
Excavation 4/4/2024 Partial Inspection JONATHAN HOM
Deputy Grading 4/5/2024 Conditional Approval MATTHEW JENKINS
Rough 4/5/2024 Not Ready for Inspection MATTHEW JENKINS
Sub-Drain 4/8/2024 Not Ready for Inspection JONATHAN HOM
Bottom/Toe 4/9/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 4/9/2024 Approved JONATHAN HOM
Excavation 4/9/2024 Not Ready for Inspection JONATHAN HOM
Deputy Grading 4/10/2024 Approved JONATHAN HOM
Bottom/Toe 4/11/2024 Partial Inspection JONATHAN HOM
Deputy Grading 4/11/2024 Approved JONATHAN HOM
Rough 4/11/2024 Partial Inspection JONATHAN HOM
Deputy Grading 4/12/2024 Approved JONATHAN HOM
Excavation 4/12/2024 Partial Inspection JONATHAN HOM
Sub-Drain 4/16/2024 Not Ready for Inspection JONATHAN HOM
Excavation 4/18/2024 Partial Inspection JONATHAN HOM
Bottom/Toe 4/19/2024 Not Ready for Inspection JONATHAN HOM
Excavation 4/24/2024 Partial Inspection JONATHAN HOM
Fill/Backfill 4/24/2024 Partial Inspection JONATHAN HOM
Initial Grading 4/24/2024 Partial Inspection JONATHAN HOM
Deputy Grading 4/25/2024 Approved JONATHAN HOM
Initial Grading 4/25/2024 Partial Inspection JONATHAN HOM
Deputy Grading 4/26/2024 Approved JONATHAN HOM
Excavation 4/26/2024 Partial Inspection JONATHAN HOM
Sub-Drain 4/29/2024 Partial Inspection JONATHAN HOM
Excavation 4/30/2024 Partial Inspection JONATHAN HOM
Bottom/Toe 5/1/2024 Partial Inspection JONATHAN HOM
Rough 5/2/2024 No Access for Inspection JONATHAN HOM
Bottom/Toe 5/6/2024 Corrections Issued ALEXANDER HELFER
Fill/Backfill 5/8/2024 Partial Inspection JONATHAN HOM
Deputy Grading 5/30/2024 Approved JONATHAN HOM
Excavation 5/30/2024 Partial Inspection JONATHAN HOM
Rough 7/15/2024 Partial Inspection JONATHAN HOM