2818 N EFFIE ST 90026
Certificate Information: 2818 N EFFIE ST 90026
- Application / Permit
- 19026-20000-00240
- Plan Check / Job No.
- B19VN07149
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- REMOVE AND REPLACE DAMAGED DRIVEWAY FOOTING AND CONCRETE STEPS DUE TO WATER DAMAGE, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/17/2021
Permit Application Status History
| Submitted | 5/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | RARES BODEA |
| Corrections Issued | 5/19/2019 | RARES BODEA |
| Quality Review Completed | 5/21/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 6/20/2019 | RARES BODEA |
| Plan Check Approved | 6/29/2020 | RARES BODEA |
| No Progress | 6/29/2020 | RARES BODEA |
| Plan Check Approved | 6/29/2020 | RARES BODEA |
| Plan Check Approved | 3/11/2021 | RARES BODEA |
| Issued | 3/26/2021 | APPLICANT |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| Permit Finaled | 8/17/2021 | THOMAS LOGRASSO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 6/5/2019 | GUILLERMO PETRA |
| Work Adjacent to Public Way | Cleared | 6/5/2019 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 6/20/2019 | RARES BODEA |
Contact Information
| Contractor | Tatum Hill Construction; Lic. No.: 1035535-B | 5142 VENICE BLVD LOS ANGELES, CA 90019 |
| Engineer | Rana,, Masood Sarwar; Lic. No.: C70659 | 19560 SHADOW RIDGE WY NORTHRIDGE, CA 91326 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
| Geologist | Van, Meter, James L.; Lic. No.: EG2031 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Corrections Issued | ROBERT VORHIS |
| Piling/Pier/Caisson | 4/21/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Piling/Pier/Caisson | 6/9/2021 | Partial Inspection | ROBERT VORHIS |
| Reinforced Concrete Frame | 6/22/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 6/23/2021 | Approved | ALFREDO BALANDRA |
| Excavation/Setback/Form/Re-Bar | 7/13/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/13/2021 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/15/2021 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/15/2021 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 7/16/2021 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 7/26/2021 | Approved | THOMAS LOGRASSO |
| Final | 7/30/2021 | Corrections Issued | THOMAS LOGRASSO |
| Final | 8/17/2021 | Permit Finaled | THOMAS LOGRASSO |