1660 W ANAHEIM ST 90731
Certificate Information: 1660 W ANAHEIM ST 90731
- Application / Permit
- 19020-40000-02777
- Plan Check / Job No.
- B19SP01579
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Installation of foundation for ammonia storage tank (1 of 3)
- Permit Issued
- Issued on 4/14/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/5/2021
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | KAVIAN REFAHI |
| Corrections Issued | 11/4/2019 | KAVIAN REFAHI |
| Quality Review Completed | 11/14/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/22/2020 | KAVIAN REFAHI |
| Issued | 4/14/2020 | APPLICANT |
| Building Plans Picked Up | 4/20/2020 | APPLICANT |
| Permit Finaled | 3/5/2021 | JOEY BUCHANAN |
Permit Application Clearance Information
| CPC | Cleared | 11/20/2019 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | PHILLIP WILSON |
| Low Impact Development | Cleared | 12/17/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/17/2019 | PHILLIP WILSON |
| Excavation more than 5-ft deep | Cleared | 1/22/2020 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 1/22/2020 | KAVIAN REFAHI |
Contact Information
| Contractor | Arb Inc; Lic. No.: 194079-A | 26000 COMMERCENTRE DRIVE LAKE FOREST, CA 92630 |
| Engineer | Lu,, Xiao Feng; Lic. No.: C82589 | 2109 MONTEVERDE DR CHINO HILLS, CA 91709 |
| Engineer | Patil,, Uday Keshav; Lic. No.: GE670 | 4011 P V DRIVE SOUTH RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/28/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/5/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/8/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/14/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/19/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/5/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/5/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/6/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/9/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 12/14/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 12/15/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 1/21/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 1/22/2021 | Approved | JOEY BUCHANAN |
| Final | 1/27/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 2/12/2021 | Conditional Approval | JOEY BUCHANAN |
| Final | 3/5/2021 | Permit Finaled | JOEY BUCHANAN |