1660 W ANAHEIM ST 90731

Certificate Information: 1660 W ANAHEIM ST 90731

Application / Permit
19020-40000-02777
Plan Check / Job No.
B19SP01579
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
Installation of foundation for ammonia storage tank (1 of 3)
Permit Issued
Issued on 4/14/2020
Issuing Office
Current Status
Permit Finaled on 3/5/2021

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 KAVIAN REFAHI
Corrections Issued 11/4/2019 KAVIAN REFAHI
Quality Review Completed 11/14/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/22/2020 KAVIAN REFAHI
Issued 4/14/2020 APPLICANT
Building Plans Picked Up 4/20/2020 APPLICANT
Permit Finaled 3/5/2021 JOEY BUCHANAN

Permit Application Clearance Information

CPC Cleared 11/20/2019 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 12/17/2019 PHILLIP WILSON
Low Impact Development Cleared 12/17/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/17/2019 PHILLIP WILSON
Excavation more than 5-ft deep Cleared 1/22/2020 CALOSHA APPROVED
Grading Pre-Inspection Cleared 1/22/2020 KAVIAN REFAHI

Contact Information

Contractor Arb Inc; Lic. No.: 194079-A 26000 COMMERCENTRE DRIVE      LAKE FOREST, CA 92630
Engineer Lu,, Xiao Feng; Lic. No.: C82589 2109 MONTEVERDE DR      CHINO HILLS, CA 91709
Engineer Patil,, Uday Keshav; Lic. No.: GE670 4011 P V DRIVE SOUTH      RANCHO PALOS VERDES, CA 90275

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/28/2020 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 10/5/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 10/8/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 10/14/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 10/19/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/5/2020 Approved JOEY BUCHANAN
Footing/Foundation/Slab 11/5/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/6/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 11/9/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 12/14/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 12/15/2020 Approved JOEY BUCHANAN
Deputy Steel/Welding 1/21/2021 Approved JOEY BUCHANAN
Deputy Steel/Welding 1/22/2021 Approved JOEY BUCHANAN
Final 1/27/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Final 2/12/2021 Conditional Approval JOEY BUCHANAN
Final 3/5/2021 Permit Finaled JOEY BUCHANAN