12324 W 25TH HELENA DR 90049

Certificate Information: 12324 W 25TH HELENA DR 90049

Application / Permit
19020-30000-03618
Plan Check / Job No.
B19WL07264
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
Two new retaining walls
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
Permit Finaled on 1/18/2024

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 MANUEL GARCIA
Corrections Issued 2/28/2020 MANUEL GARCIA
Quality Review Completed 3/6/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/3/2020 MANUEL GARCIA
Applicant returned to address corrections 10/14/2020 MANUEL GARCIA
Green Plans Picked Up 11/9/2020 APPLICANT
Applicant returned to address corrections 11/24/2020 MANUEL GARCIA
Applicant returned to address corrections 12/15/2020 MANUEL GARCIA
Plan Check Approved 1/12/2021 MANUEL GARCIA
Building Plans Picked Up 1/14/2021 APPLICANT
Issued 2/4/2021 APPLICANT
Permit Finaled 1/18/2024 JOHNNY MIRANDA

Permit Application Clearance Information

ZI Cleared 10/2/2020 RICHARD REASER
Landscape for retaining wall Cleared 10/6/2020 RICHARD REASER
Grading Pre-Inspection Cleared 1/12/2021 MANUEL GARCIA

Contact Information

Architect Barber,, Charles Timothy; Lic. No.: C29232 829 N HARPER AVENUE      LOS ANGELES, CA 90046
Contractor Premier General Contractors Inc; Lic. No.: 638046-B 1131 N GRANADA AVE      ALHAMBRA, CA 91801
Engineer Ruan,, Federico R; Lic. No.: S6689 553 S OAK KNOLL AVE      PASADENA, CA 91101

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/16/2021 Not Ready for Inspection JUAN VALENZUELA
Piling/Pier/Caisson 3/24/2021 Partial Approval BRIAN OLSON
Excavation/Setback/Form/Re-Bar 4/19/2021 Partial Approval KIRK LINKLATER
Deputy Reinf. Concrete 4/20/2021 Conditional Approval BRIAN OLSON
Excavation/Setback/Form/Re-Bar 4/26/2021 Partial Approval BRIAN OLSON
Masonry Wall/Backfill 5/7/2021 Partial Approval BRIAN OLSON
Excavation/Setback/Form/Re-Bar 5/19/2021 Partial Approval BRIAN OLSON
Excavation/Setback/Form/Re-Bar 6/3/2021 Partial Approval BRIAN OLSON
Masonry Wall/Backfill 6/18/2021 Partial Approval BRIAN OLSON
Final 11/28/2023 Not Ready for Inspection CHARLES POWELL
Final 1/18/2024 Permit Finaled JOHNNY MIRANDA