1821 S REDONDO BLVD 90019
Certificate Information: 1821 S REDONDO BLVD 90019
- Application / Permit
- 19020-30000-03401
- Plan Check / Job No.
- B19WL06864
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Fence Wall
- Work Description
- NEW 6-'0" HT FENCE WALL ALONG REAR AND SIDE PROPERTY LINES, PER ENGINEERING.
- Permit Issued
- Issued on 2/19/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/28/2020
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2019 | SERGIO SILVA |
| Corrections Issued | 12/10/2019 | SERGIO SILVA |
| Plan Check Approved | 2/7/2020 | REZA HAGHIGHAT |
| Issued | 2/19/2020 | LADBS |
| Permit Finaled | 4/27/2020 | SCOTT FINNILA |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/5/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/5/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Century 26 Construction Inc; Lic. No.: 1056879-B | 269 S BEVERLY DR #263 BEVERLY HILLS, CA 90212 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/9/2020 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 3/10/2020 | Partial Approval | SCOTT FINNILA |
| Pre-Inspection | 3/10/2020 | No Result Entered | ELMER BLAND |
| Pre-Inspection | 3/10/2020 | Off-Hour Fees Due | |
| Masonry Wall/Backfill | 3/20/2020 | Conditional Approval | SCOTT FINNILA |
| Masonry Wall/Backfill | 3/25/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Masonry | 3/26/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Masonry Wall/Backfill | 3/26/2020 | No Result Entered | MICHAEL FAUNCE |
| Excavation/Setback/Form/Re-Bar | 4/3/2020 | No Result Entered | MICHAEL FAUNCE |
| Excavation/Setback/Form/Re-Bar | 4/3/2020 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/4/2020 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/7/2020 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/24/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 4/27/2020 | Permit Finaled | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/27/2020 | Approved | SCOTT FINNILA |