2407 N WILD OAK DR 90068

Certificate Information: 2407 N WILD OAK DR 90068

Application / Permit
19020-30000-02805
Plan Check / Job No.
B19WL05742
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) RETAINING WALL & OUTDOOR PATIO AT EAST SIDE OF PROPERTY.
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
Issued on 12/10/2020

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 JAHANSHAH POURHASSAN
Corrections Issued 10/31/2019 JAHANSHAH POURHASSAN
Quality Review Completed 11/7/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/8/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 12/2/2020 JAHANSHAH POURHASSAN
Plan Check Approved 12/3/2020 JAHANSHAH POURHASSAN
Building Plans Picked Up 12/4/2020 APPLICANT
Issued 12/10/2020 APPLICANT

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 12/3/2020 CALOSHA APPROVED
Grading Pre-Inspection Cleared 12/3/2020 JAHANSHAH POURHASSAN

Contact Information

Architect Rabin,, Daniel H; Lic. No.: C36893 1655 N BENTON WAY      LOS ANGELES, CA 90026
Contractor Lefevre Timothy F General Contractor; Lic. No.: 480271-B 3760 MAYFAIR DRIVE      LOS ANGELES, CA 90065
Engineer Amoroso,, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717
Engineer Su,, Yu-Ting; Lic. No.: C76714 28 SAGE      LAKE FOREST, CA 92630
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Concrete Frame 1/25/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/16/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/5/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 4/26/2021 Partial Approval BRIAN SULLIVAN
Reinforced Concrete Frame 6/16/2021 Not Ready for Inspection BRIAN SULLIVAN
Reinforced Concrete Frame 7/26/2021 Partial Approval RICHARD STEINBACH