1090 N ACANTO PL 90049
Certificate Information: 1090 N ACANTO PL 90049
- Application / Permit
- 19020-30000-02551
- Plan Check / Job No.
- B19WL05300
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- site retaining walls (154' north, 208' east)
- Permit Issued
- Issued on 6/26/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/26/2020
Permit Application Status History
| Submitted | 9/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | TARIK SAOUD |
| Corrections Issued | 10/7/2019 | TARIK SAOUD |
| Quality Review Completed | 10/11/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Plan Check Approved | 5/21/2020 | TARIK SAOUD |
| Issued | 6/26/2020 | LADBS |
Permit Application Clearance Information
| CPC | Cleared | 10/17/2019 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2019 | CATHERINE ADROVER |
| Miscellaneous | Cleared | 10/17/2019 | SARAH GOLDMAN |
| Low Impact Development | Cleared | 10/31/2019 | MARTIN FRAGOSO |
| Excavation more than 5-ft deep | Cleared | 5/5/2020 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/5/2020 | TARIK SAOUD |
| Construction near power lines | Cleared | 5/6/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 11/4/2022 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Corrections Issued | AL GAMBLE |
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Partial Approval | MICHAEL TEMPLE |
| Reinforced Masonry Frame | 5/11/2023 | Approved | VASIL MIHALEV |
| Deputy Reinf. Masonry | 5/12/2023 | Approved | VASIL MIHALEV |
| Reinforced Masonry Frame | 11/15/2023 | Corrections Issued | CHARLES POWELL |
| Reinforced Masonry Frame | 3/5/2024 | Approved | ROBERT PINA |
| Footing/Foundation/Slab | 9/12/2024 | Corrections Issued | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 3/26/2025 | Conditional Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 3/28/2025 | Corrections Issued | MATTHEW JENKINS |
| Deputy Reinf. Concrete | 6/9/2025 | Conditional Approval | MATTHEW JENKINS |