1531 S WALGROVE AVE 90066
Certificate Information: 1531 S WALGROVE AVE 90066
- Application / Permit
- 19020-30000-01614
- Plan Check / Job No.
- B19WL03325
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Fence Wall
- Work Description
- NEW 6" CMU WALL 6'-0" HT ALONG SIDE AND REAR OF THE PROPERTY AND 3'-6" HT IN THE REQUIRED FRONT YARD PER I.B. P/BC 2014-096.
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/26/2023
Permit Application Status History
| Submitted | 6/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | SERGIO SILVA |
| Corrections Issued | 6/13/2019 | SERGIO SILVA |
| Plan Check Approved | 7/9/2019 | JAHANSHAH POURHASSAN |
| Issued | 7/7/2020 | APPLICANT |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| Permit Finaled | 4/25/2023 | EVAN COOPER |
Permit Application Clearance Information
| CPC | Cleared | 6/20/2019 | DIANA JIMENEZ |
| CPC | Cleared | 6/20/2019 | DIANA JIMENEZ |
| Construction near power lines | Cleared | 7/3/2019 | WALTER RAMIREZ |
| Construction within easement | Cleared | 7/3/2019 | WALTER RAMIREZ |
Contact Information
| Architect | Magruder,, Stuart C; Lic. No.: C28769 | 4337 WEST 59TH STREET LOS ANGELES, CA 90043 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/8/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 7/16/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 7/16/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 7/22/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 8/4/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 8/20/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 8/28/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 9/4/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 9/9/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 9/22/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 10/6/2020 | Partial Approval | DAVID HEINE |
| Masonry Wall/Backfill | 10/9/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 5/12/2021 | Partial Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 6/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 8/26/2021 | Partial Approval | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 9/27/2021 | Approved | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 10/26/2021 | Corrections Issued | DAVID FEILER |
| Final | 4/25/2023 | Permit Finaled | EVAN COOPER |