255 N ASHDALE AVE 90049
Certificate Information: 255 N ASHDALE AVE 90049
- Application / Permit
- 19020-30000-01471
- Plan Check / Job No.
- B19WL02971
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- Retaining wall.
- Permit Issued
- Issued on 8/29/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/15/2023
Permit Application Status History
| Submitted | 5/29/2019 | APPLICANT |
| Green Plans Picked Up | 6/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 7/1/2019 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 7/12/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/28/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 8/29/2020 | APPLICANT |
| Building Plans Picked Up | 12/11/2020 | APPLICANT |
| Permit Finaled | 12/15/2023 | CHARLES POWELL |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 1/15/2020 | SARAH GOLDMAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/9/2020 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Other (see comments) | 10/13/2020 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 10/13/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/14/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/15/2020 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 10/15/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/16/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 10/21/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 11/2/2020 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/12/2020 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/16/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 11/30/2020 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/1/2020 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/1/2020 | Partial Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 12/1/2020 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 12/1/2020 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 12/2/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Other (see comments) | 12/2/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/3/2020 | Conditional Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 12/4/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/7/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 12/7/2020 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 12/16/2020 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 12/16/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/5/2021 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 1/5/2021 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/6/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/8/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 1/12/2021 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/4/2021 | Partial Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 2/5/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 2/9/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 2/10/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 2/23/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/4/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 3/18/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 4/1/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 4/14/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Other (see comments) | 4/28/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 4/30/2021 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | CARLOS MATAMOROS |
| Deputy Other (see comments) | 8/2/2022 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 3/29/2023 | Approved | CARLOS MATAMOROS |
| Final | 12/15/2023 | Permit Finaled | CHARLES POWELL |