1963 N STRADELLA ROAD 90077
Certificate Information: 1963 N STRADELLA ROAD 90077
- Application / Permit
- 19020-30000-00851
- Plan Check / Job No.
- B19WL01680
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) SITE RETAINING WALLS
- Permit Issued
- Issued on 7/22/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/27/2025
Permit Application Status History
| Submitted | 3/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 4/15/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 4/17/2019 | CORA JOHNSON |
| Green Plans Picked Up | 4/30/2019 | APPLICANT |
| Applicant returned to address corrections | 5/30/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/20/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/19/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/4/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/7/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 5/28/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 7/22/2020 | APPLICANT |
| Building Plans Picked Up | 8/7/2020 | APPLICANT |
| Permit Finaled | 6/26/2025 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 8/19/2019 | CALOSHA APPROVED |
| Landscape for retaining wall | Cleared | 9/4/2019 | NOAH MCCOY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Eftekhari,, Hossein; Lic. No.: C50121 | 5945 SETTLER COURT ANAHEIM, CA 92807 |
| Engineer | Naim,, Soleiman Israel; Lic. No.: S2454 | 403 21ST ST SANTA MONICA, CA 90402 |
| Geologist | Bramwell,, David Delton; Lic. No.: EG112 | GLOBAL GEOLOGICAL SERVICES 983 RIDGEWOOD DR CORONA, CA 91719 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/14/2021 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/14/2021 | Approved | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 10/14/2021 | Approved | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 1/10/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/12/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 2/22/2022 | Partial Approval | CHRISTOPHER WILSON |
| Structural Steel Frame | 2/24/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/4/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/18/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/13/2022 | Partial Approval | CHRISTOPHER WILSON |
| Final | 6/26/2025 | Permit Finaled | CHRISTOPHER WILSON |