12326 W LAUREL TERRACE DR 91604
Certificate Information: 12326 W LAUREL TERRACE DR 91604
- Application / Permit
- 19020-20001-00528
- Plan Check / Job No.
- B19VN17039
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- SUPPLEMENTAL PERMIT TO EXTEND PROPOSED RETAINING WALL BY 63 LINEAR FT. SEE COMMENTS.
- Permit Issued
- Issued on 4/27/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/7/2021
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/9/2019 | JEROME MAGAT PALMA |
| Issued | 4/27/2020 | APPLICANT |
| Permit Finaled | 5/7/2021 | KIRK LINKLATER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/4/2019 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian,, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
| Geologist | Hill,, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2020 | Approved | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/22/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/29/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 6/8/2020 | Corrections Issued | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 7/8/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 7/16/2020 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 8/13/2020 | No Access for Inspection | KIRK LINKLATER |
| Footing/Foundation/Slab | 8/14/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 8/21/2020 | Approved | ALEXANDER HELFER |
| Masonry Wall/Backfill | 9/2/2020 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 11/9/2020 | Corrections Issued | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 1/6/2021 | Approved | VASIL MIHALEV |
| Deputy Shotcrete | 1/12/2021 | Conditional Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Corrections Issued | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 4/1/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 4/6/2021 | Partial Approval | TIMOTHY POWELL |
| Deputy Reinf. Masonry | 4/21/2021 | Approved | PATRICK MISCHLICH |
| Final | 4/23/2021 | Not Ready for Inspection | KIRK LINKLATER |
| Final | 5/7/2021 | Permit Finaled | KIRK LINKLATER |