3413 N NORTH KNOLL DR 90068
Certificate Information: 3413 N NORTH KNOLL DR 90068
- Application / Permit
- 19020-20000-03372
- Plan Check / Job No.
- B19VN21222
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13'-6" X 15'-0" OPEN TRELLIS, 26'-9" X 19'-6" DECK & 6'-0" X 10'-2" BREEZWAY ADDITION TO (E) SFD PER ENGINEERING.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 12/21/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 12/23/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Plan Check Approved | 2/28/2020 | ARTIN ZARUKIAN |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 9/1/2021 | BRIAN SULLIVAN |
| Permit Finaled | 1/14/2022 | DEROLD HAUFF |
| CofO Issued | 1/14/2022 | DEROLD HAUFF |
| Permit Finaled | 1/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/22/2019 | ARTIN ZARUKIAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | GUILLERMO PETRA |
| Miscellaneous | Cleared | 2/3/2020 | GUILLERMO PETRA |
| Specific Plan | Cleared | 2/28/2020 | DOMINICK ORTIZ |
| ZI | Cleared | 2/28/2020 | DOMINICK ORTIZ |
Contact Information
| Contractor | A List Builders Inc; Lic. No.: 952112-B | 13237 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/12/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 6/15/2020 | Approved | BRIAN SULLIVAN |
| Final | 8/9/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/9/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 8/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 8/9/2021 | Corrections Issued | BRIAN SULLIVAN |
| Final | 8/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 8/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 8/20/2021 | Corrections Issued | BRIAN SULLIVAN |
| Final | 8/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 8/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 8/27/2021 | Approved | BRIAN SULLIVAN |
| Final | 8/31/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| Smoke Detectors | 8/31/2021 | Approved | BRIAN SULLIVAN |