10664 N ENCINO AVE 91344
Certificate Information: 10664 N ENCINO AVE 91344
- Application / Permit
- 19020-20000-03129
- Plan Check / Job No.
- B19VN19642
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (61) Use of Land
- Work Description
- USE OF LAND TO RE-STRIPE (E) PARKING LOT FOR OFFSITE PARKING REQUIRED FOR (N) MIXED USE BLDG UNDER PERMIT NO. 17010-20000-01261
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- CofO Issued on 11/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/25/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/25/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/25/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 11/25/2019 | APPLICANT |
| Applicant returned to address corrections | 7/30/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/24/2021 | NILOOFAR MEHRAIN |
| Issued | 12/10/2021 | APPLICANT |
| CofO in Progress | 11/16/2023 | JEFFREY FULTON |
| CofO Issued | 11/16/2023 | JEFFREY DURAN |
| Permit Finaled | 11/16/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2020 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 7/22/2020 | NILOOFAR MEHRAIN |
| Driveway location | Cleared | 8/18/2020 | BRANDON WILSON |
| Internal circulation | Cleared | 8/18/2020 | BRANDON WILSON |
| Miscellaneous | Cleared | 11/25/2020 | MIGUEL GAMBOA |
| Prkng lot landscape/Water mgmt | Cleared | 11/25/2020 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 11/25/2020 | MIGUEL GAMBOA |
| ZI | Cleared | 11/25/2020 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Jasco Enterprise Inc; Lic. No.: 871467-B | 12439 MAGNOLIA BL 185 VALLEY VILLAGE, CA 91607 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/5/2023 | Partial Inspection | JEFFREY FULTON |
| Special/Order Compliance | 10/11/2023 | Conditional Approval | JEFFREY FULTON |
| Final | 11/17/2023 | OK to Issue CofO | JEFFREY FULTON |