2712 W LYTELLE PL 90065
Certificate Information: 2712 W LYTELLE PL 90065
- Application / Permit
- 19020-20000-02678
- Plan Check / Job No.
- B19VN16723
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- SHORING FOR SFD/ GAR
- Permit Issued
- Issued on 11/17/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/20/2023
Permit Application Status History
| Submitted | 10/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | BINH PHAN |
| Plans on Hold | 10/10/2019 | BINH PHAN |
| No Progress | 9/15/2020 | YAQUB MIRZA |
| Hold Released | 9/15/2020 | YAQUB MIRZA |
| Plan Check Approved | 9/15/2020 | YAQUB MIRZA |
| Issued | 11/17/2020 | APPLICANT |
| Building Plans Picked Up | 11/25/2020 | APPLICANT |
| Permit Finaled | 3/16/2023 | LANNY MERRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/15/2020 | YAQUB MIRZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khaliq,, Shehzad; Lic. No.: S4390 | 3456 GOLDEN POPPY WAY YORBA LINDA, CA 92886 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2020 | Partial Approval | CRAIG VAUGHAN |
| Deputy Grading | 4/13/2021 | No Access for Inspection | ELMER BLAND |
| Piling/Pier/Caisson | 4/29/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Piling/Pier/Caisson | 5/3/2021 | Corrections Issued | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 5/4/2021 | Corrections Issued | CRAIG VAUGHAN |
| Special/Order Compliance | 5/4/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 5/20/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 5/21/2021 | Partial Approval | ALEXANDER HELFER |
| Piling/Pier/Caisson | 6/1/2021 | Partial Approval | ROBERT HUGHES |
| Piling/Pier/Caisson | 7/20/2021 | Partial Approval | ROBERT HUGHES |
| Piling/Pier/Caisson | 7/28/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Piling/Pier/Caisson | 7/30/2021 | Partial Approval | ROBERT HUGHES |
| Piling/Pier/Caisson | 10/22/2021 | Not Ready for Inspection | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Piling/Pier/Caisson | 11/17/2021 | Partial Approval | ROBERT HUGHES |
| Final | 2/10/2023 | Not Ready for Inspection | LANNY MERRICK |
| Final | 3/16/2023 | Permit Finaled | LANNY MERRICK |