10132 N COMMERCE AVE #1-37 91042

Certificate Information: 10132 N COMMERCE AVE #1-37 91042

Application / Permit
19020-20000-02603
Plan Check / Job No.
B19VN16259
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING ON PILES FOR 3-STORY APT BLDG W/ BASEMENT GARAGE
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
Permit Finaled on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 NILOOFAR MEHRAIN
Disabled Access Plans Picked Up 10/29/2019 APPLICANT
Green Plans Picked Up 10/29/2019 APPLICANT
Corrections Issued 10/30/2019 NILOOFAR MEHRAIN
Quality Review Completed 10/31/2019 GUANG MIN TUNG
Building Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 8/11/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/6/2020 NILOOFAR MEHRAIN
Plan Check Approved 1/26/2021 NILOOFAR MEHRAIN
Issued 2/17/2021 APPLICANT
Permit Finaled 12/14/2023 DANNY RODRIGUEZ

Permit Application Clearance Information

Encroachment in public way Cleared 11/18/2019 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 11/18/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/10/2020 APEKSHYA BAJRACHARYA
Excavation more than 5-ft deep Cleared 8/11/2020 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 10/15/2020 GABRIEL ROBLES
Miscellaneous Cleared 1/20/2021 DANG NGUYEN
Specific Plan Cleared 1/20/2021 DANG NGUYEN
ZI Cleared 1/20/2021 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/1/2021 Not Ready for Inspection ANDREW DORSO
Deputy Grading 3/15/2021 Approved HAMID PISHEHVAR
Deputy Grading 3/16/2021 Conditional Approval ANDREW DORSO
Deputy Grading 3/17/2021 Conditional Approval ANDREW DORSO
Deputy Grading 3/18/2021 Conditional Approval ANDREW DORSO
Deputy Grading 3/19/2021 Conditional Approval ANDREW DORSO
Deputy Grading 3/23/2021 Conditional Approval ANDREW DORSO
Deputy Grading 3/24/2021 Conditional Approval ANDREW DORSO
Deputy Grading 3/25/2021 Conditional Approval JEFFREY DURAN
Deputy Grading 3/26/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 3/30/2021 Partial Inspection DANNY RODRIGUEZ
Deputy Grading 3/31/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Grading 4/1/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/6/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/7/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/8/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/13/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/14/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Grading 4/15/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/19/2021 Approved DANNY RODRIGUEZ
Deputy Grading 4/20/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 5/18/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/19/2021 Partial Approval DANNY RODRIGUEZ
Deputy Grading 6/2/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Grading 6/3/2021 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 6/3/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Grading 6/4/2021 Approved DANNY RODRIGUEZ