13119 W BEAVER ST 91342
Certificate Information: 13119 W BEAVER ST 91342
- Application / Permit
- 19020-20000-02598
- Plan Check / Job No.
- B19VN16187
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW (8 FT MAX) SITE RET WALL. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/12/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/9/2021
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | TROY DEGUZMAN |
| Corrections Issued | 10/22/2019 | TROY DEGUZMAN |
| Quality Review Completed | 10/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Applicant returned to address corrections | 2/12/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 4/30/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 6/12/2020 | TROY DEGUZMAN |
| Plan Check Approved | 6/12/2020 | TROY DEGUZMAN |
| Issued | 6/12/2020 | APPLICANT |
| Permit Finaled | 6/8/2021 | KIRK LINKLATER |
Permit Application Clearance Information
| Construction within easement | Cleared | 2/27/2020 | OSCAR CASTRO |
| GPI Written Notices | Cleared | 4/30/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 4/30/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Jin; Lic. No.: C64433 | 5 MONTELENA IRVINE, CA 92602 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Engineer | Um,, Bin; Lic. No.: C59287 | 2708 FOOTHILL BLVD #205 LA CRESCENTA, CA 91214 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/30/2020 | Approved | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 7/30/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall | 8/5/2020 | Corrections Issued | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 8/14/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall | 8/24/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Rough | 10/7/2020 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 10/20/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall | 10/27/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall | 12/3/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall | 12/9/2020 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall | 2/12/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 3/18/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Reinforced Masonry Frame | 4/7/2021 | Partial Approval | TIMOTHY POWELL |
| Final | 4/20/2021 | Partial Inspection | MATTHEW JENKINS |
| Masonry Wall/Backfill | 5/21/2021 | Corrections Issued | MATTHEW JENKINS |
| Final | 6/8/2021 | Permit Finaled | KIRK LINKLATER |