16751 W CHARMEL LANE 90272
Certificate Information: 16751 W CHARMEL LANE 90272
- Application / Permit
- 19020-20000-02595
- Plan Check / Job No.
- B19VN16151
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL (MAX 4' HIGH, APPROX 62 LINEAR FEET)
- Permit Issued
- Issued on 8/24/2020
- Issuing Office
- Current Status
- Issued on 8/24/2020
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | SELLA BENYAMIN |
| Green Plans Picked Up | 10/3/2019 | APPLICANT |
| Corrections Issued | 10/7/2019 | SELLA BENYAMIN |
| Quality Review Completed | 10/8/2019 | STEVEN KIM |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Applicant returned to address corrections | 5/19/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 6/2/2020 | SELLA BENYAMIN |
| Plan Check Approved | 6/17/2020 | SELLA BENYAMIN |
| Issued | 8/24/2020 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pacific Point Builders Inc; Lic. No.: 768984-B | 18340 VENTURA BLVD STE 210 TARZANA, CA 91356 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/9/2020 | Corrections Issued | MATTHEW JENKINS |
| Footing/Foundation/Slab | 10/22/2020 | Partial Approval | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 10/30/2020 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 10/30/2020 | Partial Inspection | MATTHEW JENKINS |
| Masonry Wall/Backfill | 11/20/2020 | Partial Approval | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 12/10/2020 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 12/10/2020 | Partial Approval | MATTHEW JENKINS |
| Masonry Wall/Backfill | 12/21/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Masonry Wall/Backfill | 12/23/2020 | Partial Approval | BRIAN OLSON |
| Footing/Foundation/Slab | 2/2/2021 | Partial Approval | KIRK LINKLATER |
| Masonry Wall/Backfill | 2/10/2021 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 2/25/2021 | Partial Inspection | MATTHEW JENKINS |
| Masonry Wall/Backfill | 2/25/2021 | Partial Inspection | MATTHEW JENKINS |
| Final | 6/5/2026 | Not Ready for Inspection | RUSSELL BONVOULOIR |