1165 N SOMERA ROAD 90077

Certificate Information: 1165 N SOMERA ROAD 90077

Application / Permit
19020-20000-02131
Plan Check / Job No.
B19VN13052
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
TWO (N) 10FT HIGH MAX RETAINING ( 1 @ 235LF & 1 @ 423.5LF) ON PILES
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
Permit Finaled on 12/31/2025

Permit Application Status History

Submitted 8/5/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 NILOOFAR MEHRAIN
Green Plans Picked Up 9/12/2019 APPLICANT
Corrections Issued 9/19/2019 NILOOFAR MEHRAIN
Quality Review Completed 9/19/2019 GUANG MIN TUNG
Building Plans Picked Up 10/10/2019 APPLICANT
Applicant returned to address corrections 10/24/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/23/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/19/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/7/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/26/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/22/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 5/18/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/1/2021 NILOOFAR MEHRAIN
Plan Check Approved 6/3/2021 NILOOFAR MEHRAIN
Issued 6/29/2021 APPLICANT
Permit Finaled 12/31/2025 RUSSELL BONVOULOIR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/22/2019 ADRIAN CASTRO
Grading Pre-Inspection Cleared 5/18/2021 NILOOFAR MEHRAIN
Miscellaneous Cleared 6/8/2021 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 6/8/2021 MAHELET GEBEYHU
Landscape for retaining wall Cleared 6/11/2021 LAUREN PADICK
Excavation more than 5-ft deep Cleared 6/14/2021 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Geologist Miller,, Steven Burl; Lic. No.: EG1303 23890 COPPERHILL DRIVE #111      VALENCIA, CA 91354

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/3/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 5/6/2022 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/24/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 5/27/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/1/2022 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 6/1/2022 Partial Approval CHARLES POWELL
Reinforced Concrete Frame 6/16/2022 Partial Approval CHARLES POWELL
Special/Order Compliance 6/16/2022 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 7/1/2022 Partial Approval CHARLES POWELL
Reinforced Concrete Frame 7/1/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 7/6/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/21/2022 Approved CHARLES POWELL
Piling/Pier/Caisson 7/21/2022 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 7/22/2022 Partial Approval CHARLES POWELL
Piling/Pier/Caisson 7/22/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 7/25/2022 Partial Approval CHARLES POWELL
Reinforced Concrete Frame 7/25/2022 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 8/12/2022 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 8/25/2022 Partial Approval CHARLES POWELL
Deputy Drilled-In Anchors 9/19/2022 Approved CHARLES POWELL
Deputy Other (see comments) 9/22/2022 Partial Approval CHARLES POWELL
Deputy Shotcrete 9/29/2022 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 11/9/2022 Partial Approval CHARLES POWELL
Reinforced Concrete Frame 11/9/2022 Partial Approval CHARLES POWELL
Deputy Shotcrete 11/10/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 5/8/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 5/17/2023 Approved VASIL MIHALEV
Deputy Reinf. Concrete 7/12/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/8/2024 Partial Inspection MATTHEW JENKINS
Piling/Pier/Caisson 1/8/2024 Partial Inspection MATTHEW JENKINS
Special/Order Compliance 1/9/2024 Corrections Issued MATTHEW JENKINS
Footing/Foundation/Slab 1/12/2024 Not Ready for Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 1/17/2024 Partial Approval MANUEL TEJADA
Footing/Foundation/Slab 1/17/2024 Partial Approval MANUEL TEJADA
Piling/Pier/Caisson 1/17/2024 Not Ready for Inspection MANUEL TEJADA
Wood Frame 2/13/2024 Partial Approval JOHNNY MIRANDA
Reinforced Concrete Frame 8/7/2024 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 11/20/2024 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/8/2025 Partial Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 7/18/2025 Not Ready for Inspection LANNY MERRICK
Excavation/Setback/Form/Re-Bar 8/4/2025 Partial Approval LANNY MERRICK
Final 12/31/2025 Permit Finaled RUSSELL BONVOULOIR