4021 N ROYAL OAK PL 91436
Certificate Information: 4021 N ROYAL OAK PL 91436
- Application / Permit
- 19020-20000-01631
- Plan Check / Job No.
- B19VN09920
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- -2-NEW RETAINING WALL ON PILES, Max. 10'-H, 266'-L
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/31/2022
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Green Plans Picked Up | 6/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | CHON CHIO KUO |
| Corrections Issued | 7/15/2019 | CHON CHIO KUO |
| Quality Review Completed | 7/17/2019 | STEVEN KIM |
| Building Plans Picked Up | 7/17/2019 | APPLICANT |
| Applicant returned to address corrections | 8/13/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/12/2019 | CHON CHIO KUO |
| Plan Check Approved | 12/20/2019 | CHON CHIO KUO |
| Issued | 1/3/2020 | LADBS |
| Permit Finaled | 3/31/2022 | TIMOTHY POWELL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Landscape for retaining wall | Cleared | 7/25/2019 | STEVEN WECHSLER |
| Excavation more than 5-ft deep | Cleared | 9/12/2019 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/12/2019 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 9/12/2019 | CHON CHIO KUO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 2/24/2020 | Approved | ALEXANDER ANDREWS |
| Piling/Pier/Caisson | 3/6/2020 | Conditional Approval | ALEXANDER ANDREWS |
| Structural Steel Frame | 3/6/2020 | Partial Approval | ALEXANDER ANDREWS |
| Piling/Pier/Caisson | 3/20/2020 | Conditional Approval | ALEXANDER ANDREWS |
| Deputy Grading | 5/11/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Drilled-In Anchors | 9/22/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Shotcrete | 9/23/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Shotcrete | 9/24/2020 | Approved | ALEXANDER ANDREWS |
| Deputy Shotcrete | 9/30/2020 | No Access for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 9/30/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Piling/Pier/Caisson | 9/30/2020 | Not Ready for Inspection | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 10/2/2020 | No Access for Inspection | BARTON HOLMES |
| Deputy Shotcrete | 10/5/2020 | Approved | ALEXANDER ANDREWS |
| Final | 3/10/2022 | No Access for Inspection | MANUEL TEJADA |
| Final | 3/11/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 3/21/2022 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 3/31/2022 | Permit Finaled | TIMOTHY POWELL |