7711 N CANOGA AVE 91304
Certificate Information: 7711 N CANOGA AVE 91304
- Application / Permit
- 19020-20000-00707
- Plan Check / Job No.
- B19VN04150
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (61) Use of Land
- Work Description
- ADD (21) TIME FILL POSTS FOR (E) PRIVATE NATURAL GAS FUELING STATION
- Permit Issued
- Issued on 9/14/2020
- Issuing Office
- Current Status
- CofO Issued on 2/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | NILOOFAR MEHRAIN |
| Disabled Access Plans Picked Up | 4/16/2019 | APPLICANT |
| Corrections Issued | 4/22/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/23/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 4/30/2019 | APPLICANT |
| Plan Check Approved | 3/12/2020 | NILOOFAR MEHRAIN |
| Issued | 9/14/2020 | APPLICANT |
| CofO in Progress | 2/3/2022 | JEFFREY FULTON |
| Permit Finaled | 2/16/2022 | JEFFREY DURAN |
| CofO Issued | 2/16/2022 | JEFFREY DURAN |
| Permit Finaled | 2/16/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | JOHN LIN |
| ZA Case | Cleared | 2/13/2020 | VINCENT QUITORIANO |
| ZA Case | Cleared | 2/13/2020 | VINCENT QUITORIANO |
| ZA Case | Cleared | 2/13/2020 | VINCENT QUITORIANO |
| DAS Clearance | Cleared | 3/4/2020 | NILOOFAR MEHRAIN |
| Gasoline station | Cleared | 3/12/2020 | SCAQMD APPROVED |
Contact Information
| Contractor | Amtek Construction; Lic. No.: 490382-B | 946 N LEMON STREET ORANGE, CA 92867 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/19/2021 | No Access for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 1/20/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/20/2021 | Corrections Issued | JEFFREY FULTON |
| Footing/Foundation/Slab | 3/8/2021 | Approved | JEFFREY FULTON |
| Deputy Reinf. Concrete | 3/11/2021 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Concrete | 3/12/2021 | Conditional Approval | JEFFREY FULTON |
| Final | 10/19/2021 | OK to Issue CofO | JEFFREY FULTON |