7875 W GRANITO DR 90046
Certificate Information: 7875 W GRANITO DR 90046
- Application / Permit
- 19020-20000-00139
- Plan Check / Job No.
- B19VN00996
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- TWO (N) 10FT HIGH MAX (1535LF) RETAINING WALLS ON PILES PER ENG'R DESIGN
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/12/2023
Permit Application Status History
| Submitted | 2/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/20/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 2/25/2019 | APPLICANT |
| Green Plans Picked Up | 2/25/2019 | APPLICANT |
| Applicant returned to address corrections | 5/8/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/20/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/16/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/3/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/26/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/18/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/7/2020 | NILOOFAR MEHRAIN |
| Issued | 8/6/2020 | APPLICANT |
| Permit Finaled | 4/11/2023 | ALEXANDER HELFER |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 3/5/2019 | TREVOR MARTIN |
| Tract Map conditions | Cleared | 3/5/2019 | TREVOR MARTIN |
| GPI Written Notices | Cleared | 5/8/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 5/8/2019 | NILOOFAR MEHRAIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2019 | JEANETTE VONG |
| Work Adjacent to Public Way | Cleared | 7/22/2019 | BOK GOH |
| ZA Case | Cleared | 7/8/2020 | NOAH MCCOY |
| Landscape for retaining wall | Cleared | 7/15/2020 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 7/24/2020 | NGOC KIEM |
Contact Information
| Contractor | Hill Pete Construction Company Inc; Lic. No.: 470065-B | 4626 ALBUQUERQUE ST 2ND FLOOR SAN DIEGO, CA 92109 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Zweigler,, Robert Ingraham; Lic. No.: EG1210 | 196 DIRT ROAD THOUSAND OAKS, CA 91361 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Approved | VASIL MIHALEV |
| Pre-Inspection | 9/15/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 9/18/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 9/18/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 9/24/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 10/1/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 10/8/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 10/14/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 10/29/2020 | Approved | VASIL MIHALEV |
| Masonry Wall/Backfill | 11/9/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 11/13/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 12/10/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 12/17/2020 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Approved | ALEXANDER HELFER |
| Piling/Pier/Caisson | 12/22/2020 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 1/6/2021 | Approved | ALEXANDER HELFER |
| Masonry Wall/Backfill | 1/14/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 1/19/2021 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 1/19/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Piling/Pier/Caisson | 1/19/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 1/21/2021 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 1/21/2021 | Approved | ALEXANDER HELFER |
| Piling/Pier/Caisson | 1/21/2021 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 1/22/2021 | Partial Approval | ALEXANDER HELFER |
| Footing/Foundation/Slab | 1/22/2021 | Approved | ALEXANDER HELFER |
| Piling/Pier/Caisson | 1/22/2021 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 1/25/2021 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 1/25/2021 | Approved | ALEXANDER HELFER |
| Piling/Pier/Caisson | 1/25/2021 | Approved | ALEXANDER HELFER |
| Piling/Pier/Caisson | 1/27/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 2/2/2021 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 2/2/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 2/4/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Piling/Pier/Caisson | 2/9/2021 | Not Ready for Inspection | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 2/10/2021 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 2/10/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 2/16/2021 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 2/16/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 4/15/2021 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Approved | VASIL MIHALEV |
| Masonry Wall/Backfill | 4/22/2021 | Approved | VASIL MIHALEV |
| Final | 2/7/2023 | Partial Inspection | ALEXANDER HELFER |
| Final | 4/11/2023 | Permit Finaled | ALEXANDER HELFER |