4046 N STRAWBERRY PL 91436

Certificate Information: 4046 N STRAWBERRY PL 91436

Application / Permit
19020-20000-00105
Plan Check / Job No.
B19VN00731
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 12' HIGH MAX, 114' LONG RETAINING WALL. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 9/1/2020
Issuing Office
Valley
Current Status
Permit Finaled on 11/8/2021

Permit Application Status History

Submitted 1/16/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 GURUNATH NESARAJAH
Corrections Issued 2/6/2019 GURUNATH NESARAJAH
Quality Review Completed 2/7/2019 OMID HEDAYAT
Building Plans Picked Up 2/7/2019 APPLICANT
Plan Check Approved 1/8/2020 GURUNATH NESARAJAH
Issued 9/1/2020 APPLICANT
Permit Finaled 11/8/2021 RONALD COWAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2019 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 3/4/2019 LEE GUILBEAUX
ZA Case Cleared 3/4/2019 RICK TORRES
Grading Pre-Inspection Cleared 7/17/2019 GURUNATH NESARAJAH
Landscape for retaining wall Cleared 7/18/2019 ANNA VIDAL

Contact Information

Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 11/13/2020 Partial Approval RONALD COWAN
Excavation/Setback/Form/Re-Bar 11/23/2020 Partial Approval RONALD COWAN
Piling/Pier/Caisson 11/23/2020 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 12/1/2020 Approved RONALD COWAN
Deputy Reinf. Concrete 12/2/2020 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 12/4/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 3/26/2021 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 3/31/2021 Approved RONALD COWAN
Footing/Foundation/Slab 4/5/2021 Approved RONALD COWAN
Masonry Wall/Backfill 4/5/2021 Partial Approval RONALD COWAN
Masonry Wall/Backfill 4/21/2021 Approved RONALD COWAN
Final 7/8/2021 Corrections Issued RONALD COWAN
Final 7/27/2021 No Access for Inspection DAVID SANDOVAL
Final 11/8/2021 Permit Finaled RONALD COWAN