1260 S FIGUEROA ST 90015

Certificate Information: 1260 S FIGUEROA ST 90015

Application / Permit
19020-10001-01762
Plan Check / Job No.
B19LA23704
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
PROPOSED REVISIONS TO SHORING FOR A 38 STORY HOTEL, RETAIL AND PARKING GARAGE, BEING ISSUED UNDER 19010-10000-01188 TWO LEVELS OF BASEMENT ADDING LOT 13 AT THE CORNER OF SITE TO PLANS.
Permit Issued
Issued on 12/12/2019
Issuing Office
Metro
Current Status
Permit Finaled on 2/11/2023
Certificate of Occupancy
CofO Corrected More Information

Permit Application Status History

Plan Check Approved 11/6/2019 JOHN VASQUEZ
Issued 12/12/2019 LADBS
Permit Finaled 2/10/2023 JAMES POWERS

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 11/6/2019 CALOSHA APPROVED
City owned building/parcel Cleared 11/14/2019 HAROOT AVANESIAN
Eng Process Fee Ord 176,300 Cleared 12/9/2019 PAMELA TENEZA
Highway dedication Cleared 12/9/2019 ERIK BEASLEY
Encroachment in public way Cleared 12/10/2019 ELENA LOPEZ
Work Adjacent to Public Way Cleared 12/10/2019 BOK GOH

Contact Information

Contractor Calex Engineering Company; Lic. No.: 1035841-A 23651 PINE STREET      NEWHALL, CA 91321
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/17/2020 Partial Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 7/30/2020 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/31/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/1/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/2/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/3/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/4/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/8/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/11/2020 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/11/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 9/14/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/16/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/17/2020 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 10/2/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/3/2020 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 10/3/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/7/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 10/8/2020 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 10/9/2020 Not Ready for Inspection NICK DANERI
Light Gage Steel Frame 10/12/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 10/14/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 10/14/2020 Partial Approval NICK DANERI
Reinforced Masonry Frame 10/14/2020 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 10/19/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 10/22/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 10/26/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 10/28/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 10/29/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/5/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 11/10/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 11/12/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 11/17/2020 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 11/19/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 11/23/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 11/30/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 12/3/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 12/7/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 12/22/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 12/23/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Partial Approval NICK DANERI
Reinforced Concrete Frame 1/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 1/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/18/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/21/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/25/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/27/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 1/28/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 2/1/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 2/4/2021 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 2/5/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 2/9/2021 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 2/10/2021 Partial Approval DANIEL MC AULIFFE
Masonry Wall/Backfill 2/11/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/15/2021 Partial Approval DAVID TSAU
Footing/Foundation/Slab 2/16/2021 Not Ready for Inspection NICK DANERI
Masonry Wall/Backfill 2/17/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/17/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 2/23/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 3/1/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/2/2021 Partial Approval NICK DANERI
Reinforced Masonry Frame 3/4/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 3/8/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 3/9/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 3/23/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/29/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 3/29/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 3/30/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 4/6/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 4/12/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/13/2021 Partial Approval NICK DANERI
Light Gage Steel Frame 4/15/2021 Partial Inspection DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 4/20/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 4/27/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 4/29/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/3/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/4/2021 Partial Approval NICK DANERI
Reinforced Concrete Frame 5/4/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/6/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/11/2021 Partial Approval NICK DANERI
Final 2/10/2023 Permit Finaled JAMES POWERS