2840 E LUGO ST 90023
Certificate Information: 2840 E LUGO ST 90023
- Application / Permit
- 19020-10000-03629
- Plan Check / Job No.
- B19LA27271
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) Site Retaining wall on property lines
- Permit Issued
- Issued on 5/12/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/12/2023
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | HERNAN ARREOLA |
| Corrections Issued | 1/29/2020 | HERNAN ARREOLA |
| Quality Review Completed | 2/5/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 2/6/2020 | APPLICANT |
| Plan Check Approved | 6/11/2020 | HERNAN ARREOLA |
| Issued | 5/12/2021 | APPLICANT |
| Permit Finaled | 1/11/2023 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2020 | WALLIE JONG |
| Work Adjacent to Public Way | Cleared | 4/20/2020 | BOK GOH |
Contact Information
| Contractor | Anvil Construction Company Inc; Lic. No.: 998987-B | 8895 RESEARCH DRIVE IRVINE, CA 92618 |
| Engineer | Anderson,, Brett Leslie; Lic. No.: C45389 | 77009 CALIFORNIA DR PALM DESERT, CA 92211 |
| Engineer | Dizon,, Marites Avante; Lic. No.: C61180 | 3518 ATWATER AVE LOS ANGELES, CA 90039 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/20/2021 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 9/22/2021 | Partial Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Partial Approval | DANIEL COLLINS |
| Pre-Inspection | 9/30/2021 | Partial Inspection | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 10/14/2021 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 10/19/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Masonry | 10/22/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 10/28/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 11/1/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 11/5/2021 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 12/22/2021 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 3/17/2022 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Conditional Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/12/2022 | Conditional Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Partial Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 9/15/2022 | Partial Approval | MARK FERRARI |
| Masonry Wall | 9/16/2022 | Approved | RAFAEL ESPINOZA |
| Final | 10/19/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 12/20/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 1/4/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 1/11/2023 | Permit Finaled | RAFAEL ESPINOZA |