200 E WASHINGTON BLVD 90015

Certificate Information: 200 E WASHINGTON BLVD 90015

Application / Permit
19020-10000-03552
Plan Check / Job No.
B19LA26875
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING WITH LAGGING & SOLDIER PILES WITH MAX. HEIGHT OF 21' FOR NEW 4-STORY TYPE V-A 105 UNIT MIXED-USE APARTMENT BUILDING WITH OFFICE & RESIDENTIAL UNITS AT GROUND FLOOR & OVER ONE LEVEL TYPE I-A SUBTERRANIAN PARKING GARAGE. (PER ZA-DIR-2018-1094-SPR)
Permit Issued
Issued on 11/23/2020
Issuing Office
Current Status
Permit Finaled on 11/1/2023

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Disabled Access Plans Picked Up 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 GARO TELMI
Corrections Issued 2/3/2020 GARO TELMI
Quality Review Completed 2/5/2020 KEN GILL
Building Plans Picked Up 2/13/2020 APPLICANT
Applicant returned to address corrections 4/6/2020 GARO TELMI
Applicant returned to address corrections 4/29/2020 GARO TELMI
Green Plans Picked Up 5/8/2020 APPLICANT
Applicant returned to address corrections 5/12/2020 GARO TELMI
Applicant returned to address corrections 6/30/2020 GARO TELMI
Applicant returned to address corrections 7/10/2020 GARO TELMI
Applicant returned to address corrections 8/20/2020 GARO TELMI
Applicant returned to address corrections 10/16/2020 GARO TELMI
Plan Check Approved 11/20/2020 GARO TELMI
Issued 11/23/2020 APPLICANT
Permit Finaled 10/31/2023 JAMES POWERS

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 5/20/2020 HELEN JADALI
Encroachment in public way Cleared 5/26/2020 ELENA LOPEZ
Low Impact Development Cleared 7/9/2020 MARTIN FRAGOSO
Construction near power lines Cleared 7/21/2020 RIDWAN HARDY
Construction within easement Cleared 7/21/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/28/2020 PAMELA TENEZA
Community Plan Implem. Overlay Cleared 7/29/2020 JOHN KIM
Metro Rail approval Cleared 10/7/2020 GARO TELMI
Work Adjacent to Public Way Cleared 10/16/2020 GARO TELMI
"D" conditions Cleared 11/4/2020 RICHARD REASER
Miscellaneous Cleared 11/12/2020 RICHARD REASER
Tract Map conditions Cleared 11/12/2020 RICHARD REASER
Miscellaneous Cleared 11/17/2020 LINDA MARGARET
Miscellaneous Cleared 11/17/2020 LINDA MARGARET
Miscellaneous Cleared 11/17/2020 LINDA MARGARET
Roof/Waste drainage to street Cleared 11/17/2020 LINDA MARGARET

Contact Information

Contractor Amcal General Contractors Inc; Lic. No.: 460688-B 30141 AGOURA ROAD STE 100      AGOURA HILLS, CA 91301
Engineer Berliner,, Neal David; Lic. No.: GE2576 4913 MONUMENT ST      SIMI VALLEY, CA 93063
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604
Engineer Dupont,, Armando Duarte; Lic. No.: L7780 411 JENKS CIR      CORONA, CA 92880

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 2/10/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 2/11/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 2/12/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 2/16/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 2/17/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 2/22/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 3/16/2021 Conditional Approval LANNY MERRICK
Deputy Grading 3/17/2021 Conditional Approval LANNY MERRICK
Deputy Grading 3/18/2021 Conditional Approval LANNY MERRICK
Deputy Grading 3/19/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 3/23/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 3/24/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 3/25/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 3/26/2021 Conditional Approval LANNY MERRICK
Deputy Other (see comments) 3/30/2021 Conditional Approval LANNY MERRICK
Final 10/24/2023 No Access for Inspection MARTIN TAVITIAN
Green Building Final 10/24/2023 No Access for Inspection MARTIN TAVITIAN
Special/Order Compliance 10/24/2023 No Access for Inspection MARTIN TAVITIAN
Final 10/31/2023 Permit Finaled JAMES POWERS
Green Building Final 10/31/2023 Approved JAMES POWERS