710 N VIRGIL AVE 90029

Certificate Information: 710 N VIRGIL AVE 90029

Application / Permit
19020-10000-03473
Plan Check / Job No.
B19LA26486
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
Shoring for new mixed use building.
Permit Issued
Issued on 5/17/2022
Issuing Office
Metro
Current Status
Issued on 5/17/2022

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 JOE VO
Corrections Issued 1/13/2020 JOE VO
Quality Review Completed 1/16/2020 KEN GILL
Building Plans Picked Up 1/27/2020 APPLICANT
Disabled Access Plans Picked Up 1/27/2020 APPLICANT
Applicant returned to address corrections 6/15/2020 JOE VO
Applicant returned to address corrections 8/11/2020 JOE VO
Green Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 1/11/2021 JOE VO
Applicant returned to address corrections 1/19/2021 JOE VO
Plan Check Approved 3/8/2021 JOE VO
Issued 5/17/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/17/2021 CECILIO NAVARRO
Work Adjacent to Public Way Cleared 3/4/2021 JOSE RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 8/18/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 8/22/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/23/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/24/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/25/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/26/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/29/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/30/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/31/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 9/1/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 9/2/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 9/2/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 9/12/2022 Corrections Issued TED RIES
Deputy Grading 9/13/2022 Conditional Approval TED RIES
Deputy Grading 9/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 9/20/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/20/2022 Conditional Approval TED RIES
Deputy Grading 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 10/3/2022 Conditional Approval TED RIES
Deputy Reinf. Concrete 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/4/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/18/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/1/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/15/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/19/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 12/23/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/23/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/20/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 1/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 1/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/16/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 2/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 4/11/2023 Conditional Approval TED RIES
Deputy Grading 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 5/11/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 5/16/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Grading 7/10/2023 Conditional Approval DAVID BURKHEAD
Special/Order Compliance 8/18/2023 Partial Inspection TIMOTHY POWELL
Deputy Steel/Welding 8/30/2023 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 8/31/2023 Approved VAHE KELEDJIAN
Deputy Other (see comments) 9/1/2023 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 9/1/2023 Conditional Approval DAVID BURKHEAD
Deputy Grading 9/8/2023 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 1/19/2024 Partial Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/30/2024 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/31/2024 Corrections Issued RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/29/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/4/2024 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/5/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/6/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/6/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/8/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/11/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/14/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/18/2024 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/22/2024 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/26/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/27/2024 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 3/27/2024 Corrections Issued JEFFREY FULTON
Reinforced Masonry Frame 3/29/2024 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/12/2024 Corrections Issued JEFFREY FULTON
Reinforced Masonry Frame 5/22/2024 Partial Inspection JEFFREY FULTON
Piling/Pier/Caisson 7/25/2025 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 12/12/2025 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/1/2026 No Access for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 5/1/2026 No Access for Inspection MARTIN TAVITIAN