1055 S MARIPOSA AVE 90006

Certificate Information: 1055 S MARIPOSA AVE 90006

Application / Permit
19020-10000-03365
Plan Check / Job No.
B19LA25753
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Retaining Wall
Work Description
TEMPORARY SITE SHORING AND RETAINING WALL FOR SITE PERIMETER FOR APARTMENT BUILDING UNDER 19010-10000-05471 2 OF 3
Permit Issued
Issued on 4/16/2021
Issuing Office
Metro
Current Status
Permit Finaled on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/24/2019 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 1/2/2020 APPLICANT
Corrections Issued 1/14/2020 ARMEN JIVALAGIAN
Quality Review Completed 1/27/2020 JASON HEALEY
Applicant returned to address corrections 3/20/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/26/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 3/31/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/8/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 4/16/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 6/4/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/15/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/16/2020 ARMEN JIVALAGIAN
Green Plans Picked Up 12/16/2020 APPLICANT
Applicant returned to address corrections 12/24/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 12/29/2020 ARMEN JIVALAGIAN
Plan Check Approved 3/31/2021 ARMEN JIVALAGIAN
Issued 4/16/2021 APPLICANT
Building Plans Picked Up 4/19/2021 APPLICANT
Permit Finaled 7/18/2023 NICK DANERI

Permit Application Clearance Information

City owned building/parcel Cleared 1/28/2020 HAROOT AVANESIAN
Eng Process Fee Ord 176,300 Cleared 4/16/2020 PAMELA TENEZA
Construction near power lines Cleared 5/1/2020 RIDWAN HARDY
Construction within easement Cleared 5/1/2020 RIDWAN HARDY
Work Adjacent to Public Way Cleared 11/25/2020 ROSA SILVA
Excavation more than 5-ft deep Cleared 12/28/2020 CALOSHA APPROVED
Historic Resource Verification Cleared 3/26/2021 DAVID URITA
Redevelopment Project Area Cleared 3/26/2021 DAVID URITA

Contact Information

Architect Miller,, Brent Todd; Lic. No.: C30535 10918 WAGNER STREET      CULVER CITY, CA 90230
Contractor United Building Company Inc; Lic. No.: 1034972-B 250 N. HARBOR DRIVE   SUITE 311    REDONDO BEACH, CA 90277
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Krief,, Dan Dov; Lic. No.: C76041 6420 WILSHIRE BLVD STE 1000      LOS ANGELES, CA 90048
Engineer Orue,, Aldrin Jose; Lic. No.: S4399 2015 PALOMA ST      PASADENA, CA 91104

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2021 Partial Inspection DANIEL COLLINS
Deputy Grading 4/26/2021 Conditional Approval DANIEL COLLINS
Piling/Pier/Caisson 4/26/2021 Partial Approval DANIEL COLLINS
Deputy Grading 4/27/2021 Conditional Approval DANIEL COLLINS
Piling/Pier/Caisson 4/27/2021 Partial Approval DANIEL COLLINS
Deputy Grading 5/4/2021 Conditional Approval DANIEL COLLINS
Deputy Grading 5/5/2021 Conditional Approval DANIEL COLLINS
Deputy Grading 5/10/2021 Conditional Approval KATY RAMIREZ
Deputy Grading 5/11/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 5/11/2021 Corrections Issued DANIEL COLLINS
Deputy Grading 5/12/2021 Conditional Approval DANIEL COLLINS
Deputy Grading 5/13/2021 Conditional Approval KATY RAMIREZ
Deputy Grading 5/14/2021 Conditional Approval DANIEL COLLINS
Deputy Grading 5/18/2021 Conditional Approval DANIEL COLLINS
Deputy Grading 5/19/2021 Conditional Approval DANIEL COLLINS
Piling/Pier/Caisson 5/26/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 6/16/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 6/18/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 6/30/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 7/2/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 7/9/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 7/12/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 7/14/2021 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 7/19/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 8/2/2021 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 8/13/2021 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 8/16/2021 Approved LANNY MERRICK
Deputy Reinf. Concrete 8/17/2021 Conditional Approval DANIEL COLLINS
Piling/Pier/Caisson 9/2/2021 Not Ready for Inspection DANIEL COLLINS
Piling/Pier/Caisson 9/7/2021 Partial Inspection DANIEL COLLINS
Piling/Pier/Caisson 9/9/2021 Partial Inspection DANIEL COLLINS
Piling/Pier/Caisson 9/10/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 9/24/2021 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 9/28/2021 Partial Inspection DANIEL COLLINS
Reinforced Concrete Frame 9/30/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 11/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 11/9/2021 Partial Approval DANIEL COLLINS
Final 7/18/2023 Permit Finaled NICK DANERI