4501 W COLORADO BLVD 90039

Certificate Information: 4501 W COLORADO BLVD 90039

Application / Permit
19020-10000-03289
Plan Check / Job No.
B19LA25279
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW CONTAINMENT CURB AND CONCRETE PAD FOR TWO STORAGE TANKS.
Permit Issued
Issued on 5/15/2020
Issuing Office
Current Status
CofO Issued on 12/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 KEVIN MORALES
Corrections Issued 12/10/2019 KEVIN MORALES
Quality Review Completed 12/15/2019 YOUNG KIM
Plan Check Approved 5/13/2020 KEVIN MORALES
Issued 5/15/2020 APPLICANT
Building Plans Picked Up 5/18/2020 APPLICANT
CofO in Progress 12/28/2020 EDWIN GREGORYONA
CofO in Progress 12/28/2020 EDWIN GREGORYONA
CofO Issued 12/30/2020 ERNESTO CORRAL
Permit Finaled 12/30/2020 ERNESTO CORRAL

Permit Application Clearance Information

Metro Rail approval Cleared 3/20/2020 KEVIN MORALES
ZI Cleared 3/24/2020 MAXFIELD VERMY
ZA Case Cleared 3/26/2020 MAXFIELD VERMY
Low Impact Development Cleared 5/5/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 5/12/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 5/12/2020 EMIL KYUPELYAN

Contact Information

Contractor Vertical Construction Inc; Lic. No.: 409490-B 9955 MUIRLANDS      IRVINE, CA 92618
Engineer Rounds,, Douglas Robert; Lic. No.: S5472 2134 MOOREVIEW ST      HENDERSON, NV 89012
Engineer Stiegler,, Linda Catherine; Lic. No.: C51866 833 8TH AVE S      KIRKLAND, WA 98033

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/18/2020 Approved EDWIN GREGORYONA
Deputy Other (see comments) 7/8/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 7/9/2020 Partial Approval EDWIN GREGORYONA
Piling/Pier/Caisson 7/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/10/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/13/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/15/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/15/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/16/2020 Partial Approval EDWIN GREGORYONA
Piling/Pier/Caisson 7/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/20/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/21/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/22/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/23/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/27/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/29/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 7/29/2020 Partial Approval EDWIN GREGORYONA
Piling/Pier/Caisson 7/30/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 7/31/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/3/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/5/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/7/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 8/10/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 8/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/17/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/17/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/20/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/21/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 8/27/2020 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/27/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/28/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 9/1/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 9/3/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 9/9/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Other (see comments) 9/11/2020 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 9/21/2020 Partial Approval EDWIN GREGORYONA
Final 12/18/2020 Partial Inspection EDWIN GREGORYONA
Final 12/28/2020 OK to Issue CofO EDWIN GREGORYONA