6020 W AVION DR 90045
Certificate Information: 6020 W AVION DR 90045
- Application / Permit
- 19020-10000-02659
- Plan Check / Job No.
- B19LA20663
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW LIGHT STANDARD FOR TERMINAL
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- CofO Issued on 3/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | MICHAEL PEREZ |
| Corrections Issued | 11/5/2019 | MICHAEL PEREZ |
| Quality Review Completed | 11/8/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Plan Check Approved | 12/17/2019 | MICHAEL PEREZ |
| Issued | 8/17/2020 | APPLICANT |
| CofO in Progress | 3/14/2022 | NICK LAROCCA |
| CofO Issued | 3/14/2022 | NICK LAROCCA |
| Permit Finaled | 3/14/2022 | NICK LAROCCA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | ELAINE LEI |
| Miscellaneous | Cleared | 12/11/2019 | HISASHI KOBAYAKAWA |
| ZA Case | Cleared | 12/11/2019 | ANNA VAN |
| ZA Case | Cleared | 12/11/2019 | ANNA VAN |
| Project Permit | Cleared | 12/13/2019 | MICHAEL PEREZ |
Contact Information
| Contractor | Hunt Construction Group Inc; Lic. No.: 136502-B | 7720 N 16TH STREET STE 100 PHOENIX, AZ 85020 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/22/2021 | Approved | ALAN NOVAK |
| Pre-Inspection | 1/22/2021 | Approved | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 2/4/2021 | Not Ready for Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 2/5/2021 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 2/8/2021 | Approved | ALAN NOVAK |
| Footing/Foundation/Slab | 2/9/2021 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/20/2021 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/22/2021 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 5/27/2021 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 5/28/2021 | Conditional Approval | JONATHAN ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Approved | ALAN NOVAK |
| Footing/Foundation/Slab | 6/14/2021 | Partial Approval | ALAN NOVAK |
| Final | 3/14/2022 | OK to Issue CofO | NICK LAROCCA |