2450 N GLENDOWER AVE 90027

Certificate Information: 2450 N GLENDOWER AVE 90027

Application / Permit
19020-10000-02605
Plan Check / Job No.
B19LA20231
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALL
Permit Issued
Issued on 8/10/2021
Issuing Office
Current Status
Permit Finaled on 4/10/2024

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 ZAW HAN
Corrections Issued 10/16/2019 ZAW HAN
Quality Review Completed 10/17/2019 HERNAN ARREOLA
Building Plans Picked Up 10/18/2019 APPLICANT
Green Plans Picked Up 4/3/2020 APPLICANT
Applicant returned to address corrections 4/14/2020 ZAW HAN
Applicant returned to address corrections 7/22/2021 ZAW HAN
Plan Check Approved 8/6/2021 CHIHARU SUZUKI
Issued 8/10/2021 APPLICANT
Permit Finaled 4/9/2024 RUSSELL BONVOULOIR

Permit Application Clearance Information

Low Impact Development Cleared 4/1/2021 MARTIN FRAGOSO
Construction near power lines Cleared 5/26/2021 RIDWAN HARDY
Construction within easement Cleared 5/26/2021 RIDWAN HARDY
Landscape for retaining wall Cleared 7/22/2021 DENZEL HENDERSON
Miscellaneous Cleared 7/22/2021 DENZEL HENDERSON
Miscellaneous Cleared 7/22/2021 DENZEL HENDERSON
Excavation more than 5-ft deep Cleared 7/28/2021 CALOSHA APPROVED
GPI Written Notices Cleared 7/28/2021 ROBERT HUGHES
Grading Pre-Inspection Cleared 7/28/2021 ROBERT HUGHES
Green Code Cleared 7/28/2021 ZAW HAN

Contact Information

Architect Bertram,, John; Lic. No.: C29063 673 N BERENDO STREET      LOS ANGELES, CA 90004
Contractor Golden Touch Construction Inc; Lic. No.: 892123-B 461 JESSIE STREET      SAN FERNANDO, CA 91340
Engineer Robert, Alan Hollingsworth; Lic. No.: GE2022       ,

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/20/2021 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 11/29/2021 Partial Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 12/15/2021 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 7/13/2022 Approved ROBERT HUGHES
Deputy Reinf. Concrete 7/21/2022 Approved ROBERT HUGHES
Deputy Shotcrete 7/25/2022 Approved ROBERT HUGHES
Footing/Foundation/Slab 10/5/2022 Approved ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 10/24/2022 Approved ALEXANDER HELFER
Final 4/9/2024 Permit Finaled RUSSELL BONVOULOIR
Green Building Final 4/9/2024 Approved RUSSELL BONVOULOIR