5620 W DE LONGPRE AVE 90028

Certificate Information: 5620 W DE LONGPRE AVE 90028

Application / Permit
19020-10000-02545
Plan Check / Job No.
B19LA19758
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
Early Start Permit for SHORING FOR A New 8-Story (4 levels of Type IIIA over 4 levels of Type IA) 184 Unit Apartment building over 1 level of TYPE IA subterranean parking
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
Permit Finaled on 6/9/2023

Permit Application Status History

Submitted 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 HERNAN ARREOLA
Corrections Issued 10/28/2019 HERNAN ARREOLA
Quality Review Completed 10/28/2019 BILL STUTSMAN
Building Plans Picked Up 10/29/2019 APPLICANT
Plan Check Approved 4/9/2021 HERNAN ARREOLA
Issued 4/9/2021 APPLICANT
Permit Finaled 6/8/2023 DAVID BURKHEAD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/7/2019 PAMELA TENEZA
Work Adjacent to Public Way Cleared 4/1/2021 ROSA SILVA
Low Impact Development Cleared 4/6/2021 ANDRES COVARRUBIAS
Site Plan review Cleared 4/6/2021 ERIN STRELICH
ZA Case Cleared 4/6/2021 ERIN STRELICH
ZA Case Cleared 4/6/2021 ERIN STRELICH
Eng Process Fee Ord 176,300 Cleared 4/7/2021 ELAINE LEI
Highway dedication Cleared 4/7/2021 ELAINE LEI
Project located in CRA area Cleared 4/8/2021 GISELLE CORELLA
Building over 3-story or 36-ft Cleared 4/9/2021 CALOSHA APPROVED
Construction near power lines Cleared 4/9/2021 WALTER RAMIREZ
Excavation more than 5-ft deep Cleared 4/9/2021 CALOSHA APPROVED

Contact Information

Contractor Zamborelli Enterprises; Lic. No.: 830680-A 640 SOUTH COAST HIGHWAY   #3A    LAGUNA BEACH, CA 92651
Engineer Cords,, Donald Alan; Lic. No.: GE2529 3553 TEXAS ST      SAN DIEGO, CA 92104
Engineer Young,, Don Yuk-Man; Lic. No.: C35713 149 PASADENA AVE STE B      SOUTH PASADENA, CA 91030

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2021 Partial Inspection RUSSELL BONVOULOIR
Deputy Grading 4/13/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 4/14/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 4/15/2021 Conditional Approval DAVID BURKHEAD
Deputy Grading 4/16/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 4/19/2021 Conditional Approval DAVID BURKHEAD
Piling/Pier/Caisson 4/27/2021 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/28/2021 Not Ready for Inspection DAVID BURKHEAD
Piling/Pier/Caisson 6/1/2021 Not Ready for Inspection DAVID BURKHEAD
Final 6/8/2023 Permit Finaled DAVID BURKHEAD