700 N HENRY FORD AVE 90744
Certificate Information: 700 N HENRY FORD AVE 90744
- Application / Permit
- 19020-10000-02502
- Plan Check / Job No.
- B19LA19402
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- FOR DEARATOR VESSEL REPLACEMENT PROJECT TO PROVIDE NEW OPEN FRAME STEEL SUPPORT STRUCTURE FOR VESSEL SUPPORT WITH NEW DRILLED PILE FOUNDATION
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/22/2021
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 10/8/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 11/7/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Plan Check Approved | 2/13/2020 | SAMUEL GONZALEZ |
| Issued | 9/10/2020 | APPLICANT |
| Permit Finaled | 2/22/2021 | JOEY BUCHANAN |
Permit Application Clearance Information
| ZA Case | Cleared | 11/14/2019 | ANNA VAN |
| Abandoned oil well | Cleared | 1/31/2020 | JOHN CONNEALLY |
Contact Information
| Contractor | Arb Inc; Lic. No.: 194079-A | 26000 COMMERCENTRE DRIVE LAKE FOREST, CA 92630 |
| Engineer | Kim,, Kyle Joonseop; Lic. No.: C65540 | 2700 AMHERST AVE FULLERTON, CA 92831 |
| Engineer | Patil,, Uday Keshav; Lic. No.: GE670 | 4011 P V DRIVE SOUTH RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/16/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/19/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/20/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/21/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/22/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/23/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/26/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/28/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/29/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/30/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/2/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/4/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/5/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/6/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/16/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/17/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/18/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/18/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 11/19/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 12/7/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 12/16/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 12/22/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 2/9/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 2/10/2021 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 2/11/2021 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 2/17/2021 | Approved | JOEY BUCHANAN |
| Final | 2/19/2021 | Conditional Approval | JOEY BUCHANAN |
| METHANE-Rough | 2/19/2021 | Approved | JOEY BUCHANAN |
| Reinforced Concrete Frame | 2/19/2021 | Approved | JOEY BUCHANAN |
| Final | 2/22/2021 | Permit Finaled | JOEY BUCHANAN |