4221 S REDWOOD AVE 90066
Certificate Information: 4221 S REDWOOD AVE 90066
- Application / Permit
- 19020-10000-02234
- Plan Check / Job No.
- B19LA17026
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INSTALL (39) DOUBLE MECHANICAL PARKING UNITS TO NEW CONCRETE FOOTINGS, TOTAL IS 85 TOTAL PARKING SPACES.
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 6/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | TSE MING HUANG |
| Corrections Issued | 9/16/2019 | TSE MING HUANG |
| Quality Review Completed | 9/21/2019 | STANLEY RAAP |
| Building Plans Picked Up | 10/3/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/3/2019 | APPLICANT |
| Applicant returned to address corrections | 11/1/2019 | TSE MING HUANG |
| Applicant returned to address corrections | 2/18/2020 | TSE MING HUANG |
| Plan Check Approved | 3/4/2020 | TSE MING HUANG |
| Issued | 3/4/2020 | LADBS |
| CofO in Progress | 4/14/2021 | ALAN NOVAK |
| CofO Issued-Status Void | 5/25/2021 | JONATHAN ALLEN |
| Permit Finaled-Status Void | 5/25/2021 | JONATHAN ALLEN |
| Re-Activate Permit | 6/4/2021 | JONATHAN ALLEN |
| Permit Finaled | 6/7/2021 | HENRY BAGHDASSARIAN |
| Permit Finaled | 6/7/2021 | HENRY BAGHDASSARIAN |
| CofO Corrected | 6/7/2021 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/22/2019 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | JEANETTE VONG |
| Highway dedication | Cleared | 1/31/2020 | OSCAR GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 1/31/2020 | ERIK BEASLEY |
| Specific Plan | Cleared | 2/10/2020 | FREDDY GARCIA |
| Specific Plan | Cleared | 2/14/2020 | ESTHER AMAYA |
| "D" conditions | Cleared | 2/18/2020 | JOE LUCKEY |
| Prkng lot landscape/Water mgmt | Cleared | 2/18/2020 | JOE LUCKEY |
| Construction near power lines | Cleared | 2/21/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 2/21/2020 | OSCAR CASTRO |
| DAS Clearance | Cleared | 3/2/2020 | ELIZABETH TOMS |
| Mechanical Car Lift | Cleared | 3/2/2020 | TSE MING HUANG |
Contact Information
| Architect | Deenihan,, John Gilmore; Lic. No.: C9147 | 5931 OAKDALE AVENUE WOODLAND HILLS, CA 91367 |
| Contractor | Park Plus California Turn Key Construction Inc; Lic. No.: 1018794-B | 8640 TAMRACK AVE SUN VALLEY, CA 91352 |
| Engineer | Smith,, Bradley Warren; Lic. No.: S2842 | PO BOX 1064 OJAI, CA 93024 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 4/14/2020 | Approved | ALAN NOVAK |
| Special/Order Compliance | 4/21/2020 | Approved | ALAN NOVAK |
| Pre-Inspection | 6/11/2020 | Approved | ALAN NOVAK |
| Final | 2/19/2021 | Conditional Approval | ALAN NOVAK |
| Final | 3/3/2021 | Conditional Approval | ALAN NOVAK |